4027 1/2-3/4 E BEMIS ST 90039

Certificate Information: 4027 1/2-3/4 E BEMIS ST 90039

Application / Permit
25014-10000-00447
Plan Check / Job No.
B25LA03940
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage with addition to two ADUs per GC 66323(a)(4)
Permit Issued
Issued on 3/19/2025
Issuing Office
Current Status
CofO Issued on 3/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/4/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 ALEC MOUSAKHANIAN
Corrections Issued 2/7/2025 ALEC MOUSAKHANIAN
Plan Check Approved 3/18/2025 ALEC MOUSAKHANIAN
Issued 3/19/2025 APPLICANT
CofO in Progress 3/17/2026 ALIZAH MAYAGOITIA
Permit Finaled 3/18/2026 DEROLD HAUFF
CofO Issued 3/18/2026 DEROLD HAUFF
Permit Finaled 3/18/2026 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 2/11/2025 BRENNEN OBETO
Roof/Waste drainage to street Cleared 2/14/2025 DAVID VO
Address approval Cleared 3/12/2025 DAVID VO
Hold Cleared 3/12/2025 SANDRA SOH
Eng Process Fee Ord 176,300 Cleared 3/14/2025 DAVID VO
Sewer availability Cleared 3/14/2025 DAVID VO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/22/2025 Partial Inspection NICHOLAS LOPEZ
PLUMBING-Rough 5/12/2025 Partial Approval NICHOLAS LOPEZ
Sewer 5/12/2025 Approved NICHOLAS LOPEZ
Deputy Drilled-In Anchors 5/15/2025 Conditional Approval NICHOLAS LOPEZ
Deputy Wood Construction 5/15/2025 Conditional Approval NICHOLAS LOPEZ
Deputy Drilled-In Anchors 5/19/2025 Partial Approval NICHOLAS LOPEZ
Footing/Foundation/Slab 5/19/2025 Approved NICHOLAS LOPEZ
Special/Order Compliance 5/19/2025 Corrections Issued NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 6/12/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Rough 6/12/2025 Not Ready for Inspection NICHOLAS LOPEZ
BUILDING-Rough-Frame 6/23/2025 Not Ready for Inspection DAVID WILLIAMS
Green Building Rough 6/23/2025 Not Ready for Inspection DAVID WILLIAMS
Rough-Elec/Plmb/HVAC 7/14/2025 Corrections Issued NICHOLAS LOPEZ
BUILDING-Rough-Frame 7/17/2025 Approved NICHOLAS LOPEZ
Green Building Rough 7/17/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 7/17/2025 Partial Approval NICHOLAS LOPEZ
Rough-Elec/Plmb/HVAC 7/17/2025 Approved NICHOLAS LOPEZ
Insulation 7/21/2025 Approved ALEX COLIN
Drywall Nailing 7/30/2025 Approved REGINA MENDEZ
Interior/Exterior Lathing 7/30/2025 Approved REGINA MENDEZ
ELECTRICAL-Final 12/2/2025 Corrections Issued NICHOLAS LOPEZ
Final 12/2/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 12/2/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 12/2/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 12/2/2025 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 12/2/2025 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 12/2/2025 Not Ready for Inspection NICHOLAS LOPEZ
Final 3/9/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 3/9/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Approved NICHOLAS LOPEZ
Smoke Detectors 3/9/2026 Approved NICHOLAS LOPEZ
Final 3/13/2026 Partial Approval ALIZAH MAYAGOITIA
Service/Power Release 3/13/2026 Approved ALIZAH MAYAGOITIA
Final 3/16/2026 OK to Issue CofO ALIZAH MAYAGOITIA