3033 1/2 W AVENUE 34 90065

Certificate Information: 3033 1/2 W AVENUE 34 90065

Application / Permit
25014-10000-00428
Plan Check / Job No.
B25LA03732
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE AT CENTER OF LOT WITH ADDITION TO BECOME A 1-STORY ACCESSORY DWELLING UNIT PER ORDINANCE LAMC 12.22 A.33(b)(1)3
Permit Issued
Issued on 10/2/2025
Issuing Office
Metro
Current Status
Issued on 10/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/31/2025 APPLICANT
Assigned to Plan Check Engineer 2/6/2025 JAD BASMA
Corrections Issued 2/8/2025 JAD BASMA
Quality Review Completed 2/14/2025 KEN GILL
Building Plans Picked Up 2/20/2025 APPLICANT
Plan Check Approved 8/19/2025 JAD BASMA
No Progress 8/19/2025 JAD BASMA
Plan Check Approved 10/1/2025 JAD BASMA
Issued 10/2/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/6/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 3/6/2025 DAVID LOPEZ
Grading Pre-Inspection Cleared 3/26/2025 LANNY MERRICK
Hydrant and Access approval Cleared 4/1/2025 KURT CORRAL
Tenant Habitability Plan Cleared 7/21/2025 KORNEL LELEA
Eng Process Fee Ord 176,300 Cleared 8/8/2025 RYAN CASTRO
Sewer availability Cleared 8/8/2025 RYAN CASTRO
ZI Cleared 8/13/2025 ANDREA MAGANA-WITHERS
GPI Written Notices Cleared 8/19/2025 JAD BASMA

Contact Information

Contractor Cgs Home Improvement Inc; Lic. No.: 1037939-B 7189 N FIGUEROA ST      LOS ANGELES, CA 90042
Engineer , ; Lic. No.: C93527       ,

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 10/10/2025 Partial Approval NICHOLAS LOPEZ
Footing/Foundation/Slab 10/21/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/12/2025 Corrections Issued NICHOLAS LOPEZ
HVAC-Rough 12/12/2025 Not Ready for Inspection NICHOLAS LOPEZ
PLUMBING-Rough 12/12/2025 Approved NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/9/2026 Conditional Approval NICHOLAS LOPEZ
Green Building Rough 2/9/2026 Not Ready for Inspection NICHOLAS LOPEZ
MERV13>=Rough 2/9/2026 Not Ready for Inspection NICHOLAS LOPEZ
BUILDING-Rough-Frame 2/25/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 2/25/2026 Approved NICHOLAS LOPEZ
Green Building Rough 2/25/2026 Approved NICHOLAS LOPEZ
HVAC-Rough 2/25/2026 Approved NICHOLAS LOPEZ
MERV13>=Rough 2/25/2026 Approved NICHOLAS LOPEZ
Wood Frame 2/25/2026 Approved NICHOLAS LOPEZ
Insulation 3/6/2026 Partial Approval NICHOLAS LOPEZ
Interior/Exterior Lathing 3/6/2026 Partial Approval NICHOLAS LOPEZ
Shower Pan 3/6/2026 Approved NICHOLAS LOPEZ
Drywall Nailing 3/20/2026 Approved NICHOLAS LOPEZ
Insulation 3/20/2026 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 3/20/2026 Approved NICHOLAS LOPEZ