7426 W 89TH ST 90045
Certificate Information: 7426 W 89TH ST 90045
- Application / Permit
- 25014-10000-00409
- Plan Check / Job No.
- B24LA38602
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *Eplan.* Convert (E) detached garage to ADU with (N) 1st and 2nd story additions. Resulting in 2-story ADU per LAMC 12.22 A.33(b)(1).
- Permit Issued
- Issued on 6/29/2025
- Issuing Office
- Current Status
- CofO Issued on 5/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2025 | HUAN LE |
| Corrections Issued | 2/26/2025 | HUAN LE |
| Quality Review Completed | 2/27/2025 | PRANITA SHAH |
| Applicant returned to address corrections | 5/20/2025 | HUAN LE |
| Plan Check Approved | 6/18/2025 | HUAN LE |
| Issued | 6/29/2025 | APPLICANT |
| CofO in Progress | 5/22/2026 | MICHAEL LEWIS |
| Permit Finaled | 5/23/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/23/2026 | RICHARD STEINBACH |
| CofO Issued | 5/23/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/12/2025 | VASIL MIHALEV |
| Address approval | Cleared | 3/15/2025 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 3/15/2025 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 3/22/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/22/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 3/22/2025 | LEE GUILBEAUX |
| Construction within easement | Cleared | 3/25/2025 | RIDWAN HARDY |
| Specific Plan | Cleared | 4/1/2025 | PEDRO AYALA |
| GPI Written Notices | Cleared | 5/20/2025 | HUAN LE |
Contact Information
| Contractor | John Williamson Construction Inc; Lic. No.: 451421-B | , |
| Contractor | Williamson John Construction Inc; Lic. No.: 451421-B | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: NA44672 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/16/2025 | Conditional Approval | JUAN VALENZUELA |
| Pre-Inspection | 7/18/2025 | Partial Inspection | JESUS PINEDA |
| Footing/Foundation/Slab | 7/22/2025 | Partial Approval | MICHAEL ALLEN |
| Underground Mechanical | 7/22/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 8/12/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 8/14/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 8/14/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2025 | Corrections Issued | JESUS PINEDA |
| Green Building Rough | 8/26/2025 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 11/4/2025 | Corrections Issued | JESUS PINEDA |
| HVAC-Rough | 11/4/2025 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 11/4/2025 | Approved | JESUS PINEDA |
| Sewer | 11/4/2025 | Approved | JESUS PINEDA |
| Underground Mechanical | 11/4/2025 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/6/2025 | Approved | JESUS RODRIGUEZ |
| Pre-Inspection | 11/6/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Shower Pan | 11/12/2025 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/17/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 11/17/2025 | Approved | JESUS PINEDA |
| Green Building Rough | 11/17/2025 | Approved | JESUS PINEDA |
| HVAC-Rough | 11/17/2025 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 11/17/2025 | Approved | JESUS PINEDA |
| Special/Order Compliance | 11/17/2025 | Partial Inspection | BOBBY KEY |
| Special/Order Compliance | 11/17/2025 | Partial Inspection | HERBERT GIRON |
| Special/Order Compliance | 11/17/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2025 | Partial Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 11/18/2025 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 11/25/2025 | Approved | JESUS PINEDA |
| Insulation | 11/25/2025 | Approved | JESUS PINEDA |
| Gas Test | 1/22/2026 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 4/22/2026 | Approved | JESUS PINEDA |
| Final | 4/22/2026 | Corrections Issued | JESUS PINEDA |
| Green Building Final | 4/22/2026 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 4/22/2026 | Approved | JESUS PINEDA |
| PLUMBING-Final | 4/22/2026 | Approved | JESUS PINEDA |
| SGSOV-Seismic Gas S/O Valve | 4/22/2026 | SGSOV Approved | JESUS PINEDA |
| Smoke Detectors | 4/22/2026 | Approved | JESUS PINEDA |
| Final | 5/21/2026 | OK to Issue CofO | MICHAEL LEWIS |
| Green Building Final | 5/21/2026 | Approved | MICHAEL LEWIS |