6460 W 81ST ST 90045
Certificate Information: 6460 W 81ST ST 90045
- Application / Permit
- 25014-10000-00383
- Plan Check / Job No.
- B25LA03318
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- Eplan. New 257 sf rec room attached to existing garage.
- Permit Issued
- Issued on 10/29/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2025 | ZAW HAN |
| Corrections Issued | 2/4/2025 | ZAW HAN |
| Applicant returned to address corrections | 9/25/2025 | ZAW HAN |
| Plan Check Approved | 10/5/2025 | ZAW HAN |
| Issued | 10/29/2025 | APPLICANT |
| CofO in Progress | 2/13/2026 | ANTHONY EGSON |
| Permit Finaled | 2/24/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/24/2026 | RICHARD STEINBACH |
| CofO Issued | 2/24/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 3/12/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/12/2025 | RIDWAN HARDY |
| Specific Plan | Cleared | 9/8/2025 | HAMID GHAEMMAGHAMI |
| Roof/Waste drainage to street | Cleared | 9/10/2025 | CHRISTINE REUSCH |
| Sewer availability | Cleared | 9/10/2025 | CHRISTINE REUSCH |
| CPC | Cleared | 9/12/2025 | ROSALINDA MEZA |
| CPC | Cleared | 9/12/2025 | ROSALINDA MEZA |
| CPC | Cleared | 9/12/2025 | ROSALINDA MEZA |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2025 | CHRISTINE REUSCH |
Contact Information
| Contractor | Hodges Custom Homes Inc; Lic. No.: 638808-B | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/30/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Rough | 11/18/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2025 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 12/3/2025 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 12/3/2025 | Approved | ANTHONY EGSON |
| Green Building Rough | 12/3/2025 | Approved | ANTHONY EGSON |
| Wood Frame | 12/3/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Drywall Nailing | 12/5/2025 | Approved | ANTHONY EGSON |
| Insulation | 12/5/2025 | Approved | ANTHONY EGSON |
| Final | 1/29/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 1/29/2026 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/29/2026 | SGSOV Not Required | ANTHONY EGSON |
| Final | 2/12/2026 | OK to Issue CofO | ANTHONY EGSON |
| Smoke Detectors | 2/12/2026 | Approved | ANTHONY EGSON |