4141 N COLBATH AVE 91423

Certificate Information: 4141 N COLBATH AVE 91423

Application / Permit
25014-10000-00370
Plan Check / Job No.
B25LA03176
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(E) SFD REMODEL AND DECK ADDITION WITH OPEN TRELLIS PER ENGINEER DESIGN
Permit Issued
Issued on 4/2/2025
Issuing Office
Metro
Current Status
Issued on 4/2/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/28/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 KHUONG TRUONG
Corrections Issued 2/6/2025 KHUONG TRUONG
Quality Review Completed 2/12/2025 KEN GILL
Building Plans Picked Up 2/14/2025 APPLICANT
Applicant returned to address corrections 3/20/2025 KHUONG TRUONG
Plan Check Approved 4/2/2025 KHUONG TRUONG
Issued 4/2/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/17/2025 JUSTIN BICOL
Sewer availability Cleared 3/17/2025 JUSTIN BICOL
Grading Pre-Inspection Cleared 4/2/2025 GERMAN RODRIGUEZ MENDOZA

Contact Information

Contractor Gallagher Renovations Inc; Lic. No.: 876758-B 562 SOUTH NORTON AVENUE      LOS ANGELES, CA 90020
Engineer Garza,, Omar Leonel; Lic. No.: S5593 5050 EAGLE ROCK BOULEVARD      LOS ANGELES, CA 90041

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/8/2025 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 7/14/2025 Corrections Issued MISAEL ESPARZA
HVAC-Rough 7/14/2025 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 7/14/2025 Approved MISAEL ESPARZA
ELECTRICAL-Rough 7/16/2025 Corrections Issued MISAEL ESPARZA
HVAC-Rough 7/16/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 7/21/2025 Approved KEVIN BERBERYAN
HVAC-Rough 7/21/2025 Approved KEVIN BERBERYAN
Insulation 7/25/2025 Approved JACK KARGODORIAN
Drywall Nailing 8/1/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 9/22/2025 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/6/2026 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/11/2026 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 2/12/2026 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 2/13/2026 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/20/2026 Approved MISAEL ESPARZA