1524 W GUILFORD PL 90710

Certificate Information: 1524 W GUILFORD PL 90710

Application / Permit
25014-10000-00358
Plan Check / Job No.
B25LA03052
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) 1 STORY SFD W/ATTACHED GARAGE "COMPLY WITH DEPARTMENT ORDER effective date 12/31/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 2/6/2025
Issuing Office
San Pedro
Current Status
CofO Issued on 12/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/28/2025 APPLICANT
Assigned to Plan Check Engineer 1/28/2025 CRYSTEL MAALOUF
Corrections Issued 1/28/2025 CRYSTEL MAALOUF
Plan Check Approved 1/31/2025 CARLOS MONTES
Issued 2/6/2025 APPLICANT
CofO in Progress 6/10/2025 KELLY WARNER
Permit Finaled 12/1/2025 CLAUDIO MORENO
CofO Issued 12/1/2025 CLAUDIO MORENO
Permit Finaled 12/1/2025 CLAUDIO MORENO

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/30/2025 XOCHITL ARQUIETA
Roof/Waste drainage to street Cleared 1/30/2025 XOCHITL ARQUIETA

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

KELLY WARNER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
PAUL BECKER, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
KEITH EDGHILL, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GONZALEZ, (310) 732-4530 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2025 Not Ready for Inspection KELLY WARNER
METHANE-Barrier 2/18/2025 Not Ready for Inspection KELLY WARNER
METHANE-Subgrade 2/18/2025 Not Ready for Inspection KELLY WARNER
Footing/Foundation/Slab 2/20/2025 Approved KELLY WARNER
METHANE-Barrier 2/20/2025 Approved KELLY WARNER
METHANE-Subgrade 2/20/2025 Approved KELLY WARNER
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Partial Approval KELLY WARNER
Wood Frame 3/18/2025 Approved KELLY WARNER
ELECTRICAL-Rough 3/24/2025 Not Ready for Inspection KELLY WARNER
PLUMBING-Rough 3/24/2025 Corrections Issued KELLY WARNER
Smoke Detectors 3/24/2025 Not Ready for Inspection KELLY WARNER
ELECTRICAL-Rough 3/25/2025 Partial Approval KELLY WARNER
PLUMBING-Rough 3/25/2025 Approved KELLY WARNER
ELECTRICAL-Rough 3/26/2025 Partial Approval KELLY WARNER
Insulation 3/26/2025 Approved KELLY WARNER
Smoke Detectors 3/26/2025 Not Ready for Inspection KELLY WARNER
Drywall Nailing 3/28/2025 Partial Approval KELLY WARNER
ELECTRICAL-Rough 3/28/2025 Corrections Issued KELLY WARNER
Gas Test 3/28/2025 Approved KELLY WARNER
Smoke Detectors 3/28/2025 Approved KELLY WARNER
ELECTRICAL-Rough 4/23/2025 Corrections Issued KELLY WARNER
BUILDING-Rough-Frame 5/13/2025 Approved KELLY WARNER
Final 5/13/2025 Not Ready for Inspection KELLY WARNER
Green Building Final 5/13/2025 Approved KELLY WARNER
Green Building Rough 5/13/2025 Approved KELLY WARNER
METHANE-Final 5/13/2025 Approved KELLY WARNER
METHANE-Rough 5/13/2025 Approved KELLY WARNER
SGSOV-Seismic Gas S/O Valve 5/13/2025 SGSOV Not Ready KELLY WARNER
ELECTRICAL-Final 6/10/2025 Approved KELLY WARNER
Final 6/10/2025 OK to Issue CofO KELLY WARNER
HVAC-Final 6/10/2025 Approved KELLY WARNER
Interior/Exterior Lathing 6/10/2025 Approved KELLY WARNER
PLUMBING-Final 6/10/2025 Approved KELLY WARNER
SGSOV-Seismic Gas S/O Valve 6/10/2025 SGSOV Approved KELLY WARNER