1344 W 37TH ST 90007
Certificate Information: 1344 W 37TH ST 90007
- Application / Permit
- 25014-10000-00344
- Plan Check / Job No.
- B25LA02842
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE WITH ADDITION TO ADU PER STATE LAW GCS 66323(A)(2)
- Permit Issued
- Issued on 3/17/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | ADAM HEGAZI |
| Corrections Issued | 2/1/2025 | ADAM HEGAZI |
| Building Plans Picked Up | 2/3/2025 | APPLICANT |
| Plan Check Approved | 3/17/2025 | MINA HABILI |
| Issued | 3/17/2025 | APPLICANT |
| CofO in Progress | 11/12/2025 | SABAS ALONSO |
| Permit Finaled | 11/12/2025 | DEROLD HAUFF |
| CofO Issued | 11/12/2025 | DEROLD HAUFF |
| Permit Finaled | 11/12/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/8/2025 | JESSICA OPINION |
| ZI | Cleared | 2/14/2025 | FIPE LEILUA |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 2/21/2025 | JESSICA OPINION |
| Community Plan Implem. Overlay | Cleared | 3/3/2025 | MANERI ROMAN |
| Roof/Waste drainage to street | Cleared | 3/5/2025 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Carrillo,, Jesus Eduardo; Lic. No.: C77737 | 8207 BROOKGREEN RD DOWNEY, CA 90240 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/19/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 3/20/2025 | Partial Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 4/1/2025 | Partial Approval | SABAS ALONSO |
| Sewer | 4/1/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 4/1/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 4/4/2025 | Partial Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 4/9/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/12/2025 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 5/12/2025 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 5/12/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 5/12/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 5/12/2025 | Corrections Issued | SABAS ALONSO |
| Shower Pan | 5/12/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2025 | Approved | SABAS ALONSO |
| Green Building Rough | 5/14/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 5/14/2025 | Approved | SABAS ALONSO |
| Shower Pan | 5/14/2025 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/19/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 5/19/2025 | Partial Approval | SABAS ALONSO |
| Shower Pan | 5/19/2025 | Approved | SABAS ALONSO |
| Insulation | 5/21/2025 | Corrections Issued | SABAS ALONSO |
| Insulation | 6/2/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 6/10/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/24/2025 | Approved | SABAS ALONSO |
| Final | 8/25/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 8/25/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 8/25/2025 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 8/25/2025 | Approved | BRENDAN MORELLI |
| Final | 8/28/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Final | 10/21/2025 | Corrections Issued | SABAS ALONSO |
| Final | 11/3/2025 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 11/3/2025 | Approved | SABAS ALONSO |