1344 W 37TH ST 90007

Certificate Information: 1344 W 37TH ST 90007

Application / Permit
25014-10000-00344
Plan Check / Job No.
B25LA02842
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH ADDITION TO ADU PER STATE LAW GCS 66323(A)(2)
Permit Issued
Issued on 3/17/2025
Issuing Office
Metro
Current Status
CofO Issued on 11/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/27/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 ADAM HEGAZI
Corrections Issued 2/1/2025 ADAM HEGAZI
Building Plans Picked Up 2/3/2025 APPLICANT
Plan Check Approved 3/17/2025 MINA HABILI
Issued 3/17/2025 APPLICANT
CofO in Progress 11/12/2025 SABAS ALONSO
Permit Finaled 11/12/2025 DEROLD HAUFF
CofO Issued 11/12/2025 DEROLD HAUFF
Permit Finaled 11/12/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/8/2025 JESSICA OPINION
ZI Cleared 2/14/2025 FIPE LEILUA
Eng Process Fee Ord 176,300 Cleared 2/21/2025 JESSICA OPINION
Sewer availability Cleared 2/21/2025 JESSICA OPINION
Community Plan Implem. Overlay Cleared 3/3/2025 MANERI ROMAN
Roof/Waste drainage to street Cleared 3/5/2025 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/19/2025 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 3/20/2025 Partial Inspection SABAS ALONSO
Excavation/Setback/Form/Re-Bar 4/1/2025 Partial Approval SABAS ALONSO
Sewer 4/1/2025 Approved SABAS ALONSO
Underground Mechanical 4/1/2025 Approved SABAS ALONSO
Underground Mechanical 4/4/2025 Partial Approval SABAS ALONSO
Footing/Foundation/Slab 4/9/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 5/12/2025 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 5/12/2025 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Partial Approval SABAS ALONSO
Green Building Rough 5/12/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 5/12/2025 Approved SABAS ALONSO
PLUMBING-Rough 5/12/2025 Corrections Issued SABAS ALONSO
Shower Pan 5/12/2025 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 5/14/2025 Approved SABAS ALONSO
Green Building Rough 5/14/2025 Approved SABAS ALONSO
PLUMBING-Rough 5/14/2025 Approved SABAS ALONSO
Shower Pan 5/14/2025 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 5/19/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 5/19/2025 Partial Approval SABAS ALONSO
Shower Pan 5/19/2025 Approved SABAS ALONSO
Insulation 5/21/2025 Corrections Issued SABAS ALONSO
Insulation 6/2/2025 Approved ANTHONY RAMOS
Drywall Nailing 6/10/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 6/24/2025 Approved SABAS ALONSO
Final 8/25/2025 Corrections Issued BRENDAN MORELLI
Green Building Final 8/25/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 8/25/2025 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 8/25/2025 Approved BRENDAN MORELLI
Final 8/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 8/28/2025 SGSOV Approved ALEJANDRO DE ARTOLA
Final 10/21/2025 Corrections Issued SABAS ALONSO
Final 11/3/2025 OK to Issue CofO SABAS ALONSO
Service/Power Release 11/3/2025 Approved SABAS ALONSO