531 N LUCERNE BLVD 90004
Certificate Information: 531 N LUCERNE BLVD 90004
- Application / Permit
- 25014-10000-00310
- Plan Check / Job No.
- B25LA02604
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Addition to rear of single family dwelling and remodel. Work per engineer.
- Permit Issued
- Issued on 3/13/2025
- Issuing Office
- Current Status
- CofO Issued on 4/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/28/2025 | JOHNPAUL ISIP |
| Corrections Issued | 1/30/2025 | JOHNPAUL ISIP |
| Plan Check Approved | 2/27/2025 | JOHNPAUL ISIP |
| Issued | 3/13/2025 | APPLICANT |
| CofO in Progress | 4/2/2026 | JOSH MEISTER |
| Permit Finaled | 4/3/2026 | DEROLD HAUFF |
| Permit Finaled | 4/3/2026 | DEROLD HAUFF |
| CofO Issued | 4/3/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2025 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 2/3/2025 | DAVID LOPEZ |
Contact Information
| Contractor | N A Design Builders; Lic. No.: 996566-B | , |
| Contractor | N A Designs Inc; Lic. No.: 996566-B | , |
| Engineer | Espino,, Manuel A; Lic. No.: NA55526 | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/11/2025 | Conditional Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 4/15/2025 | Approved | JEFFREY MEAD |
| METHANE-Barrier | 4/15/2025 | Approved | JEFFREY MEAD |
| METHANE-Subgrade | 4/15/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/30/2025 | Partial Approval | JEFFREY MEAD |
| Underground Mechanical | 4/30/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2025 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 7/9/2025 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 7/9/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 7/9/2025 | Not Ready for Inspection | JEFFREY MEAD |
| PLUMBING-Rough | 7/9/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 7/11/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Approved | JEFFREY MEAD |
| Green Building Rough | 7/11/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 7/11/2025 | Corrections Issued | JEFFREY MEAD |
| METHANE-Rough | 7/11/2025 | Approved | JEFFREY MEAD |
| HVAC-Rough | 7/29/2025 | Approved | JEFFREY MEAD |
| Shower Pan | 7/29/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 8/5/2025 | Corrections Issued | JEFFREY MEAD |
| Insulation | 8/11/2025 | Approved | JEFFREY MEAD |
| Drywall Nailing | 8/22/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 8/29/2025 | Partial Approval | BRENDAN MORELLI |
| Final | 2/4/2026 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 2/4/2026 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/4/2026 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 2/4/2026 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 2/13/2026 | Approved | JEFFREY MEAD |
| Final | 2/13/2026 | Partial Inspection | JEFFREY MEAD |
| HVAC-Final | 2/13/2026 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 2/13/2026 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 2/13/2026 | SGSOV Approved | JEFFREY MEAD |
| Final | 3/11/2026 | Corrections Issued | JEFFREY MEAD |
| Final | 3/27/2026 | OK to Issue CofO | JOSH MEISTER |