16825 W BAJIO ROAD 91436

Certificate Information: 16825 W BAJIO ROAD 91436

Application / Permit
25014-10000-00291
Plan Check / Job No.
B25LA02421
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: MAJOR REMODEL AND ADDITION TO (E) 2-STORY SFD WITH ATTACHED GARAGE, TRELLIS', AND PATIO COVER.
Permit Issued
Issued on 7/22/2025
Issuing Office
Current Status
Issued on 7/22/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/23/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 ADRIANA LOPEZ
Corrections Issued 2/18/2025 ADRIANA LOPEZ
Quality Review Completed 2/27/2025 HERNAN ARREOLA
Applicant returned to address corrections 6/10/2025 ADRIANA LOPEZ
Applicant returned to address corrections 7/3/2025 ADRIANA LOPEZ
Plan Check Approved 7/10/2025 ADRIANA LOPEZ
Issued 7/22/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 3/20/2025 GERMAN RODRIGUEZ MENDOZA
Eng Process Fee Ord 176,300 Cleared 4/26/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 4/26/2025 CARLOS AGUILERA
Sewer availability Cleared 4/26/2025 CARLOS AGUILERA
GPI Written Notices Cleared 6/9/2025 ADRIANA LOPEZ

Contact Information

Architect Brisley,, Lawrence Kevin; Lic. No.: NA19394       ,
Contractor Zumwalt Development Inc; Lic. No.: 1097342-B       ,
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/14/2025 Partial Approval THOMAS FINNILA
Footing/Foundation/Slab 8/29/2025 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 9/18/2025 Partial Approval THOMAS FINNILA
Deputy Steel/Welding 1/5/2026 No Access for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/22/2026 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/23/2026 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 2/26/2026 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/26/2026 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 2/26/2026 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/27/2026 Partial Approval JON MCHUGH
Special/Order Compliance 2/27/2026 Corrections Issued JON MCHUGH
ELECTRICAL-Rough 3/5/2026 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 3/5/2026 Approved THOMAS FINNILA
BUILDING-Rough-Frame 3/6/2026 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 3/6/2026 Approved THOMAS FINNILA
Green Building Rough 3/6/2026 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 3/6/2026 Corrections Issued THOMAS FINNILA
HVAC-Rough 3/13/2026 Approved THOMAS FINNILA
Shower Pan 3/13/2026 Approved THOMAS FINNILA
Wood Frame 3/13/2026 Corrections Issued THOMAS FINNILA
Interior/Exterior Lathing 3/18/2026 Partial Approval ROBERT GOLD
Interior/Exterior Lathing 4/1/2026 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 4/3/2026 Approved THOMAS FINNILA
Green Building Rough 4/3/2026 Approved THOMAS FINNILA
Insulation 4/3/2026 Approved THOMAS FINNILA
Drywall Nailing 4/14/2026 Partial Approval HENRY KIM