1509-1511 W 221ST ST 90501
Certificate Information: 1509-1511 W 221ST ST 90501
- Application / Permit
- 25014-10000-00255
- Plan Check / Job No.
- B25LA02029
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Convert portion of attached garage to living space. Add new second story for new attached ADU per CITY ORDINACE Work done per Engineer design
- Permit Issued
- Issued on 6/4/2025
- Issuing Office
- Current Status
- Issued on 6/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | KHUONG TRUONG |
| Corrections Issued | 2/4/2025 | KHUONG TRUONG |
| Quality Review Completed | 2/6/2025 | GARO TELMI |
| Plan Check Approved | 5/15/2025 | KHUONG TRUONG |
| Issued | 6/4/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2025 | FRANK SALAZAR |
| Roof/Waste drainage to street | Cleared | 4/23/2025 | FRANK SALAZAR |
| Eng Process Fee Ord 176,300 | Cleared | 4/26/2025 | FRANK SALAZAR |
| Sewer availability | Cleared | 4/26/2025 | FRANK SALAZAR |
Contact Information
| Contractor | Embark Adu; Lic. No.: 970997-B | , |
| Contractor | Esk Construction Inc; Lic. No.: 970997-B | , |
| Engineer | Braun,, Jason; Lic. No.: C70948 | 14390 SHAWNEE ST MOORPARK, CA 93021 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/13/2025 | Approved | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 6/30/2025 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 6/30/2025 | Corrections Issued | ANTHONY EGSON |
| METHANE-Barrier | 6/30/2025 | Not Ready for Inspection | ANTHONY EGSON |
| METHANE-Subgrade | 6/30/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/3/2025 | Approved | JOHN KLARIN |
| METHANE-Barrier | 7/3/2025 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 7/3/2025 | Approved | JOHN KLARIN |
| Sewer | 7/10/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2025 | Partial Approval | EUGENE CASSIDY |
| Gas Test | 10/14/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/14/2025 | Partial Approval | EUGENE CASSIDY |
| Shower Pan | 10/14/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 2/19/2026 | Partial Approval | EUGENE CASSIDY |