3746 S GREENFIELD AVE 90034

Certificate Information: 3746 S GREENFIELD AVE 90034

Application / Permit
25014-10000-00233
Plan Check / Job No.
B25LA01896
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert an existing 1-story detached 1-car Garage and addition into 580 SF detached Accessory Dwelling Unit per Ordinance and LAMC 12.22 A33(c)&(d) .All work per engineer design.
Permit Issued
Issued on 6/9/2025
Issuing Office
Current Status
CofO Issued on 12/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/20/2025 APPLICANT
Assigned to Plan Check Engineer 1/23/2025 JOSE VELAZQUEZ
Corrections Issued 1/24/2025 JOSE VELAZQUEZ
Plan Check Approved 5/27/2025 ZAW HAN
Issued 6/9/2025 APPLICANT
CofO in Progress 11/25/2025 KIRK SANDERS
Permit Finaled 12/6/2025 RICHARD STEINBACH
CofO Issued 12/6/2025 RICHARD STEINBACH
Permit Finaled 12/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/31/2025 DARIN LAM
Roof/Waste drainage to street Cleared 1/31/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 2/3/2025 DARIN LAM
Sewer availability Cleared 2/3/2025 DARIN LAM
Grading Pre-Inspection Cleared 2/4/2025 VASIL MIHALEV
Specific Plan Cleared 2/14/2025 JOSHUA JONES
Construction near power lines Cleared 5/22/2025 RIDWAN HARDY

Contact Information

Architect Gloria,, Debora; Lic. No.: NA31622       ,
Contractor G And I Construction; Lic. No.: 839295-B 339 E BRETT STREET      INGLEWOOD, CA 90302
Engineer Phillips,, Craig; Lic. No.: NA69673       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/18/2025 Conditional Approval WILBER ROSALES
Footing/Foundation/Slab 6/20/2025 Corrections Issued WILBER ROSALES
Underground Mechanical 6/20/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 7/17/2025 Approved WILBER ROSALES
Footing/Foundation/Slab 7/17/2025 Approved WILBER ROSALES
PLUMBING-Rough 7/17/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 7/22/2025 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 7/22/2025 Approved KIRK SANDERS
Green Building Rough 7/22/2025 Not Ready for Inspection KIRK SANDERS
Interior/Exterior Lathing 7/22/2025 Partial Approval KIRK SANDERS
ELECTRICAL-Rough 7/24/2025 Corrections Issued KIRK SANDERS
HVAC-Rough 7/24/2025 Corrections Issued KIRK SANDERS
PLUMBING-Final 7/24/2025 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 8/29/2025 Conditional Approval KIRK SANDERS
ELECTRICAL-Rough 8/29/2025 Approved KIRK SANDERS
Green Building Rough 8/29/2025 Approved KIRK SANDERS
HVAC-Rough 8/29/2025 Approved KIRK SANDERS
Insulation 9/3/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 9/5/2025 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 10/30/2025 Approved KIRK SANDERS
ELECTRICAL-Final 10/30/2025 Corrections Issued KIRK SANDERS
Final 10/30/2025 Corrections Issued KIRK SANDERS
Green Building Final 10/30/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Final 10/30/2025 Corrections Issued KIRK SANDERS
PLUMBING-Final 10/30/2025 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 10/30/2025 SGSOV Approved KIRK SANDERS
Smoke Detectors 10/30/2025 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 11/21/2025 Corrections Issued KIRK SANDERS
HVAC-Final 11/21/2025 Approved KIRK SANDERS
PLUMBING-Final 11/21/2025 Partial Approval KIRK SANDERS
ELECTRICAL-Final 11/24/2025 Approved KIRK SANDERS
Final 11/24/2025 OK to Issue CofO KIRK SANDERS
Green Building Final 11/24/2025 Approved KIRK SANDERS
HVAC-Final 11/24/2025 Approved KIRK SANDERS
PLUMBING-Final 11/24/2025 Approved KIRK SANDERS
Service/Power Release 11/24/2025 Approved KIRK SANDERS
Smoke Detectors 11/24/2025 Approved KIRK SANDERS