2816 S HADDINGTON DR 90064
Certificate Information: 2816 S HADDINGTON DR 90064
- Application / Permit
- 25014-10000-00178
- Plan Check / Job No.
- B25LA01417
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN-CONVERT AND ADD EXISTING DETACHED GARAGE TO ACESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) . ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/26/2025
- Issuing Office
- Current Status
- CofO Issued on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2025 | ARAMIK SHAHMIRZAIAN |
| Corrections Issued | 1/22/2025 | ARAMIK SHAHMIRZAIAN |
| Applicant returned to address corrections | 2/11/2025 | KAVIAN REFAHI |
| Applicant returned to address corrections | 2/19/2025 | ARAMIK SHAHMIRZAIAN |
| Plan Check Approved | 2/22/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 2/26/2025 | APPLICANT |
| CofO in Progress | 5/27/2026 | ASHLEY THOMPSON |
| Permit Finaled | 5/28/2026 | RICHARD STEINBACH |
| CofO Issued | 5/28/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/28/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2025 | DARIN LAM |
| Roof/Waste drainage to street | Cleared | 1/29/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2025 | DARIN LAM |
| Sewer availability | Cleared | 1/30/2025 | DARIN LAM |
| Specific Plan | Cleared | 2/6/2025 | JOSHUA JONES |
| Grading Pre-Inspection | Cleared | 2/12/2025 | VASIL MIHALEV |
Contact Information
| Architect | Abramson,, Trevor David; Lic. No.: NA17597 | , |
| Contractor | Owner-Builder | , |
| Engineer | Castro,, Ivan; Lic. No.: C84846 | 750 OTAY LAKES ROAD #202 CHULA VISTA, CA 91910 |
| Engineer | Castro,, Ivan; Lic. No.: NA84846 | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/8/2025 | Corrections Issued | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 5/9/2025 | Approved | BOBBY KEY |
| PLUMBING-Rough | 5/9/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/14/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 8/21/2025 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/21/2025 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 11/14/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 11/14/2025 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 11/14/2025 | Corrections Issued | MICHAEL ALLEN |
| Special/Order Compliance | 11/14/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 12/1/2025 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 12/8/2025 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2025 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 12/8/2025 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/8/2025 | Approved | ASHLEY THOMPSON |
| Insulation | 12/10/2025 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 12/16/2025 | Approved | EVAN COOPER |
| HVAC-Final | 4/14/2026 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 4/14/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 5/6/2026 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 5/6/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 5/6/2026 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 5/12/2026 | Approved | ASHLEY THOMPSON |
| Final | 5/12/2026 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 5/12/2026 | SGSOV Not Required | ASHLEY THOMPSON |
| Smoke Detectors | 5/12/2026 | Approved | ASHLEY THOMPSON |
| Final | 5/27/2026 | OK to Issue CofO | ASHLEY THOMPSON |