2451 S BUTLER AVE 90064
Certificate Information: 2451 S BUTLER AVE 90064
- Application / Permit
- 25014-10000-00171
- Plan Check / Job No.
- B25LA01337
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *ePlan* 2-story ground floor addition to (E) SFD. Sprinklered thru-out with NFPA-13D
- Permit Issued
- Issued on 6/4/2025
- Issuing Office
- Current Status
- CofO Issued on 2/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2025 | MATTHEW TORRES |
| Corrections Issued | 2/3/2025 | MATTHEW TORRES |
| Quality Review Completed | 2/4/2025 | GARO TELMI |
| Applicant returned to address corrections | 4/28/2025 | MATTHEW TORRES |
| Plan Check Approved | 5/6/2025 | MATTHEW TORRES |
| Issued | 6/4/2025 | APPLICANT |
| CofO in Progress | 2/11/2026 | MICHAEL ALLEN |
| CofO in Progress | 2/17/2026 | DAVID FEILER |
| Permit Finaled | 2/17/2026 | RICHARD STEINBACH |
| CofO Issued | 2/17/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/17/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/22/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 2/22/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 2/25/2025 | LEE GUILBEAUX |
| Specific Plan | Cleared | 3/17/2025 | JOSHUA JONES |
Contact Information
| Contractor | Tgibbs Construction Llc; Lic. No.: 1086590-B | , |
| Engineer | Xi,, Wang; Lic. No.: NA85148 | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/30/2025 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/3/2025 | Corrections Issued | KIRK SANDERS |
| Footing/Foundation/Slab | 7/3/2025 | Partial Approval | KIRK SANDERS |
| BUILDING-Rough-Frame | 7/22/2025 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/22/2025 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 9/10/2025 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/10/2025 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/10/2025 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 9/11/2025 | Corrections Issued | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/14/2025 | Conditional Approval | MICHAEL ALLEN |
| Green Building Rough | 10/14/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| HVAC-Rough | 10/14/2025 | Approved | MICHAEL ALLEN |
| MERV13>=Rough | 10/14/2025 | Approved | MICHAEL ALLEN |
| Wood Frame | 10/14/2025 | Approved | MICHAEL ALLEN |
| Insulation | 11/4/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 11/4/2025 | Partial Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 11/10/2025 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 11/10/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 11/10/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 11/20/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 1/28/2026 | Corrections Issued | MICHAEL ALLEN |
| Final | 1/28/2026 | Corrections Issued | MICHAEL ALLEN |
| Footing/Foundation/Slab | 1/28/2026 | Approved | MICHAEL ALLEN |
| Green Building Final | 1/28/2026 | Conditional Approval | MICHAEL ALLEN |
| HVAC-Final | 1/28/2026 | Conditional Approval | MICHAEL ALLEN |
| MERV13>=Final | 1/28/2026 | Approved | MICHAEL ALLEN |
| PLUMBING-Final | 1/28/2026 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 1/28/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 2/10/2026 | Approved | MICHAEL ALLEN |
| Final | 2/10/2026 | OK to Issue CofO | MICHAEL ALLEN |
| Green Building Final | 2/10/2026 | Approved | MICHAEL ALLEN |
| HVAC-Final | 2/10/2026 | Approved | MICHAEL ALLEN |