3774 N WILLOW CREST AVE 91604
Certificate Information: 3774 N WILLOW CREST AVE 91604
- Application / Permit
- 25014-10000-00167
- Plan Check / Job No.
- B25LA01258
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN NEW 2ND STORY ADDITION TO EXISTING SFD OVER ATTACHED GARAGE PER ENGINEER DESIGN
- Permit Issued
- Issued on 2/27/2025
- Issuing Office
- Current Status
- CofO Issued on 9/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | KHUONG TRUONG |
| Corrections Issued | 1/29/2025 | KHUONG TRUONG |
| Quality Review Completed | 1/30/2025 | GARO TELMI |
| Applicant returned to address corrections | 2/21/2025 | KHUONG TRUONG |
| Plan Check Approved | 2/26/2025 | KHUONG TRUONG |
| Issued | 2/27/2025 | APPLICANT |
| CofO in Progress | 8/18/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 9/11/2025 | RUBEN SALAS |
| CofO Issued | 9/11/2025 | RUBEN SALAS |
| Permit Finaled | 9/11/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 1/31/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 2/4/2025 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 2/5/2025 | ROBERT PINA |
| Hydrant and Access approval | Cleared | 2/18/2025 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/7/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 4/7/2025 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 4/9/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2025 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/3/2025 | Conditional Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 6/3/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 6/3/2025 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 6/3/2025 | Approved | CHRISTOPHE COCHRAN |
| MERV13>=Rough | 6/3/2025 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 6/3/2025 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 6/11/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/11/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Shower Pan | 6/11/2025 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 6/13/2025 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 6/13/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/13/2025 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 6/16/2025 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/28/2025 | Approved | JACK KARGODORIAN |
| Final | 7/28/2025 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 7/28/2025 | Approved | JACK KARGODORIAN |
| Green Building Final | 7/28/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| MERV13>=Final | 7/28/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 7/28/2025 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 7/28/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 8/7/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 8/7/2025 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 8/7/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 8/15/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |