3774 N WILLOW CREST AVE 91604

Certificate Information: 3774 N WILLOW CREST AVE 91604

Application / Permit
25014-10000-00167
Plan Check / Job No.
B25LA01258
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN NEW 2ND STORY ADDITION TO EXISTING SFD OVER ATTACHED GARAGE PER ENGINEER DESIGN
Permit Issued
Issued on 2/27/2025
Issuing Office
Current Status
CofO Issued on 9/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/14/2025 APPLICANT
Assigned to Plan Check Engineer 1/23/2025 KHUONG TRUONG
Corrections Issued 1/29/2025 KHUONG TRUONG
Quality Review Completed 1/30/2025 GARO TELMI
Applicant returned to address corrections 2/21/2025 KHUONG TRUONG
Plan Check Approved 2/26/2025 KHUONG TRUONG
Issued 2/27/2025 APPLICANT
CofO in Progress 8/18/2025 CHRISTOPHE COCHRAN
Permit Finaled 9/11/2025 RUBEN SALAS
CofO Issued 9/11/2025 RUBEN SALAS
Permit Finaled 9/11/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/31/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 1/31/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/4/2025 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 2/5/2025 ROBERT PINA
Hydrant and Access approval Cleared 2/18/2025 RUEL COLE

Contact Information

Contractor Owner-Builder       ,
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/7/2025 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 4/7/2025 Corrections Issued MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 4/9/2025 Approved KEVIN BERBERYAN
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 5/9/2025 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 6/3/2025 Conditional Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 6/3/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 6/3/2025 Approved CHRISTOPHE COCHRAN
HVAC-Rough 6/3/2025 Approved CHRISTOPHE COCHRAN
MERV13>=Rough 6/3/2025 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 6/3/2025 Approved CHRISTOPHE COCHRAN
Insulation 6/11/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/11/2025 Corrections Issued CHRISTOPHE COCHRAN
Shower Pan 6/11/2025 Approved CHRISTOPHE COCHRAN
Drywall Nailing 6/13/2025 Approved CHRISTOPHE COCHRAN
Insulation 6/13/2025 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/13/2025 Approved CHRISTOPHE COCHRAN
Drywall Nailing 6/16/2025 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 7/28/2025 Approved JACK KARGODORIAN
Final 7/28/2025 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 7/28/2025 Approved JACK KARGODORIAN
Green Building Final 7/28/2025 Not Ready for Inspection JACK KARGODORIAN
MERV13>=Final 7/28/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 7/28/2025 Not Ready for Inspection JACK KARGODORIAN
Final 8/7/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 8/7/2025 Approved CHRISTOPHE COCHRAN
Smoke Detectors 8/7/2025 Approved CHRISTOPHE COCHRAN
Final 8/15/2025 OK to Issue CofO CHRISTOPHE COCHRAN