5305-5307 N ALLOTT AVE 91401
Certificate Information: 5305-5307 N ALLOTT AVE 91401
- Application / Permit
- 25014-10000-00133
- Plan Check / Job No.
- B25LA00850
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- [ePlan] New addition and Str. remode of (E) SFD and convert (E) attached garage and (E) laundry to ADU per GC 66323(a)(1) with (N) attached Patio cover
- Permit Issued
- Issued on 2/18/2025
- Issuing Office
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 1/22/2025 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 1/29/2025 | TU HUA |
| Plan Check Approved | 2/12/2025 | MAHNAZ NOURHASHEMI |
| Issued | 2/18/2025 | APPLICANT |
| CofO in Progress | 6/27/2025 | JAVIER RAMOS JR |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
| CofO Issued | 7/31/2025 | RUBEN SALAS |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/29/2025 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 1/29/2025 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/29/2025 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2025 | EDGAR ALCARAZ |
Contact Information
| Contractor | Cali Wood Work Inc; Lic. No.: 1002653-B | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/11/2025 | Conditional Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/11/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/14/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/25/2025 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 3/25/2025 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 4/11/2025 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 4/11/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 4/11/2025 | Partial Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/23/2025 | Corrections Issued | JACK KARGODORIAN |
| HVAC-Rough | 4/23/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 4/23/2025 | Approved | JACK KARGODORIAN |
| Shower Pan | 4/24/2025 | Partial Approval | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 4/28/2025 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/28/2025 | Approved | MISAEL ESPARZA |
| Green Building Rough | 4/28/2025 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 4/28/2025 | Partial Approval | MISAEL ESPARZA |
| Shower Pan | 4/28/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 5/1/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Shower Pan | 5/1/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Special/Order Compliance | 5/1/2025 | Partial Inspection | JUAN VALENZUELA |
| Wood Frame | 5/1/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 5/5/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/7/2025 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/9/2025 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 5/9/2025 | Approved | JUAN VALENZUELA |
| Green Building Rough | 5/9/2025 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 6/23/2025 | No Access for Inspection | MISAEL ESPARZA |
| Final | 6/23/2025 | No Access for Inspection | MISAEL ESPARZA |
| Green Building Final | 6/23/2025 | No Access for Inspection | MISAEL ESPARZA |
| HVAC-Final | 6/23/2025 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 6/23/2025 | No Access for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 6/23/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 6/23/2025 | No Access for Inspection | MISAEL ESPARZA |
| Pre-Inspection | 6/25/2025 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 6/27/2025 | Approved | JAVIER RAMOS JR |
| Final | 6/27/2025 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 6/27/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 6/27/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 6/27/2025 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 6/27/2025 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 6/27/2025 | Approved | JAVIER RAMOS JR |