5305-5307 N ALLOTT AVE 91401

Certificate Information: 5305-5307 N ALLOTT AVE 91401

Application / Permit
25014-10000-00133
Plan Check / Job No.
B25LA00850
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
[ePlan] New addition and Str. remode of (E) SFD and convert (E) attached garage and (E) laundry to ADU per GC 66323(a)(1) with (N) attached Patio cover
Permit Issued
Issued on 2/18/2025
Issuing Office
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2025 APPLICANT
Assigned to Plan Check Engineer 1/16/2025 MAHNAZ NOURHASHEMI
Corrections Issued 1/22/2025 MAHNAZ NOURHASHEMI
Quality Review Completed 1/29/2025 TU HUA
Plan Check Approved 2/12/2025 MAHNAZ NOURHASHEMI
Issued 2/18/2025 APPLICANT
CofO in Progress 6/27/2025 JAVIER RAMOS JR
Permit Finaled 7/31/2025 RUBEN SALAS
CofO Issued 7/31/2025 RUBEN SALAS
Permit Finaled 7/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/29/2025 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 1/29/2025 EDGAR ALCARAZ
Sewer availability Cleared 1/29/2025 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 1/30/2025 EDGAR ALCARAZ

Contact Information

Contractor Cali Wood Work Inc; Lic. No.: 1002653-B       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/11/2025 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 3/11/2025 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 3/14/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 3/25/2025 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 3/25/2025 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 4/11/2025 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/11/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 4/11/2025 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 4/11/2025 Partial Inspection MISAEL ESPARZA
ELECTRICAL-Rough 4/23/2025 Corrections Issued JACK KARGODORIAN
HVAC-Rough 4/23/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 4/23/2025 Approved JACK KARGODORIAN
Shower Pan 4/24/2025 Partial Approval MICHAEL CORTEZ
BUILDING-Rough-Frame 4/28/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 4/28/2025 Approved MISAEL ESPARZA
Green Building Rough 4/28/2025 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 4/28/2025 Partial Approval MISAEL ESPARZA
Shower Pan 4/28/2025 Not Ready for Inspection MISAEL ESPARZA
Insulation 5/1/2025 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 5/1/2025 Not Ready for Inspection MISAEL ESPARZA
Special/Order Compliance 5/1/2025 Partial Inspection JUAN VALENZUELA
Wood Frame 5/1/2025 Not Ready for Inspection MISAEL ESPARZA
Insulation 5/5/2025 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 5/7/2025 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 5/9/2025 Approved JUAN VALENZUELA
Drywall Nailing 5/9/2025 Approved JUAN VALENZUELA
Green Building Rough 5/9/2025 Approved JUAN VALENZUELA
ELECTRICAL-Final 6/23/2025 No Access for Inspection MISAEL ESPARZA
Final 6/23/2025 No Access for Inspection MISAEL ESPARZA
Green Building Final 6/23/2025 No Access for Inspection MISAEL ESPARZA
HVAC-Final 6/23/2025 No Access for Inspection MISAEL ESPARZA
PLUMBING-Final 6/23/2025 No Access for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/23/2025 SGSOV Not Ready MISAEL ESPARZA
Smoke Detectors 6/23/2025 No Access for Inspection MISAEL ESPARZA
Pre-Inspection 6/25/2025 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Final 6/27/2025 Approved JAVIER RAMOS JR
Final 6/27/2025 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 6/27/2025 Approved JAVIER RAMOS JR
HVAC-Final 6/27/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 6/27/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/27/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 6/27/2025 Approved JAVIER RAMOS JR