7927 S AIRPORT BLVD 90045
Certificate Information: 7927 S AIRPORT BLVD 90045
- Application / Permit
- 25014-10000-00126
- Plan Check / Job No.
- B25LA00774
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan SECOND STORY ACCESSORY DWELLING UNIT ADDITION TO (E) 2-CAR GARAGE. AND NEW 29 SQ. FT. EXTERIOR STORAGE CLOSET AT FIRST FLOOR AND 21 SQFT STORAGE UNDER EXTERIOR STAIRS ADU PER ORDINANCE LAMC 12.22 A.33(b)(1)3
- Permit Issued
- Issued on 6/4/2025
- Issuing Office
- Current Status
- Issued on 6/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/23/2025 | JAD BASMA |
| Corrections Issued | 1/27/2025 | JAD BASMA |
| Quality Review Completed | 1/28/2025 | GARO TELMI |
| Applicant returned to address corrections | 5/7/2025 | JAD BASMA |
| Plan Check Approved | 5/28/2025 | JAD BASMA |
| Issued | 6/4/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/19/2025 | VASIL MIHALEV |
| Address approval | Cleared | 2/20/2025 | LIAM ODONOVAN |
| Roof/Waste drainage to street | Cleared | 2/20/2025 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/28/2025 | SAUL GARCIA |
| Sewer availability | Cleared | 3/28/2025 | SAUL GARCIA |
| Tenant Habitability Plan | Cleared | 4/1/2025 | KORNEL LELEA |
| Construction near power lines | Cleared | 4/28/2025 | ENRIQUE ACOSTA |
Contact Information
| Architect | Verdugo,, Emilio Amado; Lic. No.: NA33263 | , |
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: NA55526 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/26/2025 | Partial Approval | JESUS PINEDA |
| Deputy Drilled-In Anchors | 2/4/2026 | Conditional Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 2/10/2026 | Corrections Issued | JESUS PINEDA |
| Footing/Foundation/Slab | 2/23/2026 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2026 | Corrections Issued | JESUS PINEDA |
| Deputy Wood Construction | 5/11/2026 | Conditional Approval | DAVID FEILER |
| Sewer | 5/20/2026 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 5/20/2026 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2026 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/15/2026 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 7/15/2026 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/21/2026 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 7/21/2026 | Corrections Issued | MICHAEL LEWIS |