810 N AVENUE 65 90042
Certificate Information: 810 N AVENUE 65 90042
- Application / Permit
- 25014-10000-00123
- Plan Check / Job No.
- B25LA00755
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Rear addition and remodel for existing one story single family dwelling. All work per engineer design. "COMPLY WITH DEPARTMENT ORDER effective date 12/20/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 3/24/2025
- Issuing Office
- Current Status
- CofO Issued on 2/12/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2025 | DANIEL SANJUAN |
| Corrections Issued | 1/14/2025 | DANIEL SANJUAN |
| Applicant returned to address corrections | 1/29/2025 | DANIEL SANJUAN |
| Applicant returned to address corrections | 3/6/2025 | NGHI SU |
| Plan Check Approved | 3/23/2025 | DANIEL SANJUAN |
| Issued | 3/24/2025 | APPLICANT |
| CofO in Progress | 2/10/2026 | DANIEL DELACRUZ |
| Permit Finaled | 2/12/2026 | DANIEL SANCHEZ |
| CofO Issued | 2/12/2026 | DANIEL SANCHEZ |
| Permit Finaled | 2/12/2026 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2025 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 1/15/2025 | CELINA MORENO |
| Sewer availability | Cleared | 1/15/2025 | CELINA MORENO |
| CPC | Cleared | 1/16/2025 | JASON CHAN |
| Miscellaneous | Cleared | 1/16/2025 | EDMOND LEE |
| Zoning Information File | Cleared | 1/16/2025 | EDMOND LEE |
| Grading Pre-Inspection | Cleared | 1/21/2025 | JONATHAN HOM |
| HPOZ | Cleared | 3/5/2025 | NATHALY DE LA PAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DANIEL DELACRUZ, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO SIERRA, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT MINASSIANS, (323) 526-9348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/7/2025 | No Access for Inspection | DAVID WILLIAMS |
| Deck | 4/7/2025 | No Access for Inspection | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | No Access for Inspection | DAVID WILLIAMS |
| Footing/Foundation/Slab | 4/7/2025 | No Access for Inspection | DAVID WILLIAMS |
| Green Building Rough | 4/7/2025 | No Access for Inspection | DAVID WILLIAMS |
| Pre-Inspection | 4/7/2025 | No Access for Inspection | DAVID WILLIAMS |
| Rough-Elec/Plmb/HVAC | 4/7/2025 | No Access for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Rough | 4/8/2025 | Approved | DANIEL DELACRUZ |
| HVAC-Rough | 4/8/2025 | Approved | DANIEL DELACRUZ |
| Excavation/Setback/Form/Re-Bar | 4/15/2025 | Partial Approval | DANIEL DELACRUZ |
| Footing/Foundation/Slab | 4/23/2025 | Approved | DANIEL DELACRUZ |
| PLUMBING-Rough | 4/23/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| Shower Pan | 4/23/2025 | Approved | DANIEL DELACRUZ |
| PLUMBING-Final | 4/28/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| Wood Frame | 4/28/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| PLUMBING-Rough | 5/12/2025 | Approved | DANIEL DELACRUZ |
| Deck | 5/15/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| BUILDING-Rough-Frame | 6/17/2025 | Approved | DANIEL DELACRUZ |
| Green Building Rough | 6/17/2025 | Approved | DANIEL DELACRUZ |
| Insulation | 6/17/2025 | Approved | DANIEL DELACRUZ |
| Drywall Nailing | 6/30/2025 | Approved | PEDRO SIERRA |
| ELECTRICAL-Final | 9/9/2025 | Approved | DANIEL DELACRUZ |
| Final | 9/9/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| Green Building Final | 9/9/2025 | Approved | DANIEL DELACRUZ |
| HVAC-Final | 9/9/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| PLUMBING-Final | 9/9/2025 | Approved | DANIEL DELACRUZ |
| SGSOV-Seismic Gas S/O Valve | 9/9/2025 | SGSOV Approved | DANIEL DELACRUZ |
| Smoke Detectors | 9/9/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| Final | 9/11/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| HVAC-Final | 9/11/2025 | Approved | DANIEL DELACRUZ |
| Smoke Detectors | 9/11/2025 | Not Ready for Inspection | DANIEL DELACRUZ |
| Final | 12/30/2025 | Partial Approval | DANIEL DELACRUZ |
| Smoke Detectors | 12/30/2025 | Approved | DANIEL DELACRUZ |
| Final | 2/10/2026 | OK to Issue CofO | DANIEL DELACRUZ |