810 N AVENUE 65 90042

Certificate Information: 810 N AVENUE 65 90042

Application / Permit
25014-10000-00123
Plan Check / Job No.
B25LA00755
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Rear addition and remodel for existing one story single family dwelling. All work per engineer design. "COMPLY WITH DEPARTMENT ORDER effective date 12/20/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 3/24/2025
Issuing Office
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2025 APPLICANT
Assigned to Plan Check Engineer 1/13/2025 DANIEL SANJUAN
Corrections Issued 1/14/2025 DANIEL SANJUAN
Applicant returned to address corrections 1/29/2025 DANIEL SANJUAN
Applicant returned to address corrections 3/6/2025 NGHI SU
Plan Check Approved 3/23/2025 DANIEL SANJUAN
Issued 3/24/2025 APPLICANT
CofO in Progress 2/10/2026 DANIEL DELACRUZ
Permit Finaled 2/12/2026 DANIEL SANCHEZ
CofO Issued 2/12/2026 DANIEL SANCHEZ
Permit Finaled 2/12/2026 DANIEL SANCHEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/15/2025 CELINA MORENO
Roof/Waste drainage to street Cleared 1/15/2025 CELINA MORENO
Sewer availability Cleared 1/15/2025 CELINA MORENO
CPC Cleared 1/16/2025 JASON CHAN
Miscellaneous Cleared 1/16/2025 EDMOND LEE
Zoning Information File Cleared 1/16/2025 EDMOND LEE
Grading Pre-Inspection Cleared 1/21/2025 JONATHAN HOM
HPOZ Cleared 3/5/2025 NATHALY DE LA PAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/7/2025 No Access for Inspection DAVID WILLIAMS
Deck 4/7/2025 No Access for Inspection DAVID WILLIAMS
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 No Access for Inspection DAVID WILLIAMS
Footing/Foundation/Slab 4/7/2025 No Access for Inspection DAVID WILLIAMS
Green Building Rough 4/7/2025 No Access for Inspection DAVID WILLIAMS
Pre-Inspection 4/7/2025 No Access for Inspection DAVID WILLIAMS
Rough-Elec/Plmb/HVAC 4/7/2025 No Access for Inspection DAVID WILLIAMS
ELECTRICAL-Rough 4/8/2025 Approved DANIEL DELACRUZ
HVAC-Rough 4/8/2025 Approved DANIEL DELACRUZ
Excavation/Setback/Form/Re-Bar 4/15/2025 Partial Approval DANIEL DELACRUZ
Footing/Foundation/Slab 4/23/2025 Approved DANIEL DELACRUZ
PLUMBING-Rough 4/23/2025 Not Ready for Inspection DANIEL DELACRUZ
Shower Pan 4/23/2025 Approved DANIEL DELACRUZ
PLUMBING-Final 4/28/2025 Not Ready for Inspection DANIEL DELACRUZ
Wood Frame 4/28/2025 Not Ready for Inspection DANIEL DELACRUZ
PLUMBING-Rough 5/12/2025 Approved DANIEL DELACRUZ
Deck 5/15/2025 Not Ready for Inspection DANIEL DELACRUZ
BUILDING-Rough-Frame 6/17/2025 Approved DANIEL DELACRUZ
Green Building Rough 6/17/2025 Approved DANIEL DELACRUZ
Insulation 6/17/2025 Approved DANIEL DELACRUZ
Drywall Nailing 6/30/2025 Approved PEDRO SIERRA
ELECTRICAL-Final 9/9/2025 Approved DANIEL DELACRUZ
Final 9/9/2025 Not Ready for Inspection DANIEL DELACRUZ
Green Building Final 9/9/2025 Approved DANIEL DELACRUZ
HVAC-Final 9/9/2025 Not Ready for Inspection DANIEL DELACRUZ
PLUMBING-Final 9/9/2025 Approved DANIEL DELACRUZ
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Approved DANIEL DELACRUZ
Smoke Detectors 9/9/2025 Not Ready for Inspection DANIEL DELACRUZ
Final 9/11/2025 Not Ready for Inspection DANIEL DELACRUZ
HVAC-Final 9/11/2025 Approved DANIEL DELACRUZ
Smoke Detectors 9/11/2025 Not Ready for Inspection DANIEL DELACRUZ
Final 12/30/2025 Partial Approval DANIEL DELACRUZ
Smoke Detectors 12/30/2025 Approved DANIEL DELACRUZ
Final 2/10/2026 OK to Issue CofO DANIEL DELACRUZ