3391 S MCLAUGHLIN AVE 90066

Certificate Information: 3391 S MCLAUGHLIN AVE 90066

Application / Permit
25014-10000-00115
Plan Check / Job No.
B25LA00704
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Addition and remodel of existing 1 story single family dwelling with attached garage.
Permit Issued
Issued on 4/7/2025
Issuing Office
Current Status
CofO Issued on 11/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2025 APPLICANT
Assigned to Plan Check Engineer 1/13/2025 KELVIN CHUONG
Corrections Issued 1/14/2025 KELVIN CHUONG
Plan Check Approved 2/24/2025 ADAM HEGAZI
Issued 4/7/2025 APPLICANT
CofO in Progress 10/27/2025 KIRK SANDERS
Permit Finaled 11/8/2025 RICHARD STEINBACH
Permit Finaled 11/8/2025 RICHARD STEINBACH
CofO Issued 11/8/2025 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 1/14/2025 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 1/15/2025 DARIN LAM
Grading Pre-Inspection Cleared 1/16/2025 VASIL MIHALEV
Roof/Waste drainage to street Cleared 1/25/2025 LIAM ODONOVAN
Specific Plan Cleared 2/21/2025 PEDRO AYALA

Contact Information

Architect Ribeiro, De Moura, Ricardo Jorge; Lic. No.: C38075 5236 YARMOUTH AVE #113      ENCINO, CA 91316
Contractor Dreamers General Construction Inc; Lic. No.: 1025578-B       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/28/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 4/30/2025 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 5/1/2025 Partial Approval WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 5/27/2025 Corrections Issued WILBER ROSALES
Deputy Wood Construction 5/29/2025 Conditional Approval WILBER ROSALES
Interior/Exterior Lathing 6/3/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 6/4/2025 Approved WILBER ROSALES
ELECTRICAL-Rough 6/4/2025 Approved WILBER ROSALES
Green Building Rough 6/4/2025 Approved WILBER ROSALES
Insulation 6/6/2025 Corrections Issued WILBER ROSALES
Drywall Nailing 6/10/2025 Approved WILBER ROSALES
ELECTRICAL-Final 10/1/2025 Corrections Issued KIRK SANDERS
Final 10/1/2025 Not Ready for Inspection KIRK SANDERS
HVAC-Final 10/1/2025 Approved KIRK SANDERS
PLUMBING-Final 10/1/2025 Approved KIRK SANDERS
Final 10/27/2025 OK to Issue CofO KIRK SANDERS
Green Building Final 10/27/2025 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 10/27/2025 SGSOV Approved KIRK SANDERS
Smoke Detectors 10/27/2025 Approved KIRK SANDERS