1725 W YOSEMITE DR 90041

Certificate Information: 1725 W YOSEMITE DR 90041

Application / Permit
25014-10000-00109
Plan Check / Job No.
B25LA00680
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: ADDITION & REMODEL TO (E) SFD
Permit Issued
Issued on 2/5/2025
Issuing Office
Current Status
CofO Issued on 9/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2025 APPLICANT
Assigned to Plan Check Engineer 1/10/2025 MIROOSH KHACHATOORIAN
Corrections Issued 1/10/2025 MIROOSH KHACHATOORIAN
Plan Check Approved 2/4/2025 GURUNATH NESARAJAH
Issued 2/5/2025 APPLICANT
CofO in Progress 9/10/2025 DAVID WILLIAMS
Permit Finaled 9/13/2025 DEROLD HAUFF
CofO Issued 9/13/2025 DEROLD HAUFF
Permit Finaled 9/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/14/2025 CARLOS RAMIREZ
Sewer availability Cleared 1/14/2025 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 1/15/2025 CARLOS RAMIREZ
Grading Pre-Inspection Cleared 1/27/2025 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Partial Approval JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Not Ready for Inspection NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/9/2025 Partial Approval DAVID WILLIAMS
HVAC-Rough 4/9/2025 Partial Approval DAVID WILLIAMS
Interior/Exterior Lathing 4/9/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 4/9/2025 Approved DAVID WILLIAMS
Shower Pan 4/9/2025 Approved DAVID WILLIAMS
Drywall Nailing 4/15/2025 Approved DAVID WILLIAMS
Interior/Exterior Lathing 4/15/2025 Approved DAVID WILLIAMS
BUILDING-Rough-Frame 9/9/2025 Approved DAVID WILLIAMS
ELECTRICAL-Final 9/9/2025 Approved DAVID WILLIAMS
Final 9/9/2025 OK to Issue CofO DAVID WILLIAMS
Footing/Foundation/Slab 9/9/2025 Approved DAVID WILLIAMS
Green Building Final 9/9/2025 Approved DAVID WILLIAMS
Green Building Rough 9/9/2025 Approved DAVID WILLIAMS
HVAC-Final 9/9/2025 Approved DAVID WILLIAMS
PLUMBING-Final 9/9/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Approved DAVID WILLIAMS
Smoke Detectors 9/9/2025 Approved DAVID WILLIAMS