2191 N SUMMITRIDGE DR 90210
Certificate Information: 2191 N SUMMITRIDGE DR 90210
- Application / Permit
- 25014-10000-00108
- Plan Check / Job No.
- B24LA38425
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan - REMOVE AND REPLACE EXISTING COVERED BALCONY, 2ND STORY COVERED BALCONY ADDITION, STRUCTURAL REMODEL TO EXISTING SFD
- Permit Issued
- Issued on 3/20/2025
- Issuing Office
- Current Status
- Issued on 3/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | STARR CHEN |
| Corrections Issued | 1/23/2025 | STARR CHEN |
| Quality Review Completed | 1/23/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 3/6/2025 | STARR CHEN |
| Plan Check Approved | 3/18/2025 | STARR CHEN |
| Issued | 3/20/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/20/2025 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2025 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 3/18/2025 | STARR CHEN |
Contact Information
| Contractor | Parsa Design & Development Inc; Lic. No.: 1047027-B | , |
| Engineer | Tajvidi,, Seyed Mohammad; Lic. No.: NA84559 | , |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/26/2025 | Not Ready for Inspection | SEAN HAUPT |
| Pre-Inspection | 4/1/2025 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 6/4/2025 | Corrections Issued | SEAN HAUPT |
| HVAC-Rough | 6/4/2025 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 6/4/2025 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Rough | 6/10/2025 | Partial Approval | SEAN HAUPT |
| HVAC-Rough | 6/10/2025 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 6/10/2025 | Partial Approval | SEAN HAUPT |
| Interior/Exterior Lathing | 9/10/2025 | Approved | SEAN HAUPT |
| Special/Order Compliance | 9/10/2025 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 9/29/2025 | Corrections Issued | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 10/1/2025 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 10/1/2025 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 10/23/2025 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 10/27/2025 | Corrections Issued | SEAN HAUPT |
| Light Gage Steel Frame | 10/27/2025 | Not Ready for Inspection | SEAN HAUPT |
| Drywall Nailing | 12/15/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2025 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/9/2026 | Approved | CARLOS MATAMOROS |
| Shower Pan | 1/26/2026 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 2/3/2026 | Approved | CARLOS MATAMOROS |
| Insulation | 2/25/2026 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 4/10/2026 | Approved | CARLOS MATAMOROS |