2163-2165 N ROSCOMARE ROAD 90077

Certificate Information: 2163-2165 N ROSCOMARE ROAD 90077

Application / Permit
25014-10000-00092
Plan Check / Job No.
B25LA00576
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan. Second story addition of an Accessory Dwelling Unit to (E) one-story single family dwelling per GCS 66323(a)(1)
Permit Issued
Issued on 3/3/2025
Issuing Office
Current Status
CofO Issued on 1/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2025 APPLICANT
Assigned to Plan Check Engineer 1/30/2025 ALEXANDER JOO
Corrections Issued 2/6/2025 ALEXANDER JOO
Quality Review Completed 2/6/2025 PRANITA SHAH
Applicant returned to address corrections 2/25/2025 ALEXANDER JOO
Plan Check Approved 3/3/2025 ALEXANDER JOO
Issued 3/3/2025 APPLICANT
CofO in Progress 12/10/2025 CARLOS MATAMOROS
Permit Finaled 1/2/2026 RICHARD STEINBACH
CofO Issued 1/2/2026 RICHARD STEINBACH
Permit Finaled 1/2/2026 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/13/2025 CHARLES POWELL
Address approval Cleared 2/19/2025 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 2/19/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 2/19/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 2/19/2025 BIAINA HARITUNIAN
Sewer availability Cleared 2/19/2025 BIAINA HARITUNIAN
BHO/Hillside ordinance Cleared 2/20/2025 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 2/20/2025 HISASHI KOBAYAKAWA

Contact Information

Contractor H I C Builders Inc; Lic. No.: 1078180-B       ,
Contractor Hic Builders Inc; Lic. No.: 1078180-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: NA76761       ,

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/16/2025 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 4/16/2025 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 5/1/2025 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 6/18/2025 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Rough 6/27/2025 Approved TEMISTOCLES CAAL
HVAC-Rough 6/27/2025 Approved TEMISTOCLES CAAL
PLUMBING-Rough 6/27/2025 Approved TEMISTOCLES CAAL
Sewer 6/27/2025 Approved TEMISTOCLES CAAL
Wood Frame 7/2/2025 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 7/9/2025 Conditional Approval CHRISTOPHER WILSON
Green Building Rough 7/9/2025 Approved CHRISTOPHER WILSON
Insulation 7/9/2025 Corrections Issued CHRISTOPHER WILSON
Interior/Exterior Lathing 7/9/2025 Partial Approval CHRISTOPHER WILSON
Insulation 7/14/2025 Not Ready for Inspection MEL KHACHATOURIAN
Insulation 7/18/2025 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 7/18/2025 Corrections Issued STEPHANIE SWANSON
Drywall Nailing 7/23/2025 Approved STEPHANIE SWANSON
ELECTRICAL-Final 7/23/2025 Partial Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 7/23/2025 Partial Approval STEPHANIE SWANSON
Drywall Nailing 7/24/2025 Approved DANIEL VERA
ELECTRICAL-Final 11/4/2025 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 11/10/2025 Approved CARLOS MATAMOROS
Final 11/10/2025 Corrections Issued CARLOS MATAMOROS
Green Building Final 11/10/2025 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 11/10/2025 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 11/10/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Final 12/10/2025 Approved CARLOS MATAMOROS
Final 12/10/2025 OK to Issue CofO CARLOS MATAMOROS
HVAC-Final 12/10/2025 Approved CARLOS MATAMOROS
PLUMBING-Final 12/10/2025 Approved CARLOS MATAMOROS