137 E AVENUE 43 90031

Certificate Information: 137 E AVENUE 43 90031

Application / Permit
25014-10000-00079
Plan Check / Job No.
B24LA38382
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE PORTION OF SFD AND REAR PATIO COVER. NEW ADDITION TO SFD TO ADD 2 NEW BEDROOMS. REMODEL OF SFD THROUGHOUT TO ADD A NEW BATHROOM AND RENOVATE THE KITCHEN. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 2/12/2025
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2025 APPLICANT
Assigned to Plan Check Engineer 1/10/2025 MADISON ODELL
Corrections Issued 1/13/2025 MADISON ODELL
Applicant returned to address corrections 1/29/2025 MADISON ODELL
Applicant returned to address corrections 1/30/2025 MADISON ODELL
Applicant returned to address corrections 2/7/2025 MADISON ODELL
Plan Check Approved 2/12/2025 MADISON O'DELL
Issued 2/12/2025 APPLICANT
CofO in Progress 5/26/2026 LILIANA PORTILLO
CofO Issued 5/28/2026 DEROLD HAUFF
Permit Finaled 5/28/2026 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 1/14/2025 NATHALY DE LA PAZ
HPOZ Cleared 1/14/2025 NATHALY DE LA PAZ
Grading Pre-Inspection Cleared 1/17/2025 MICHAEL TEMPLE
Roof/Waste drainage to street Cleared 1/30/2025 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/31/2025 JEANIE LAM
Sewer availability Cleared 1/31/2025 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/14/2025 Partial Inspection LILIANA PORTILLO
Footing/Foundation/Slab 3/3/2025 Partial Approval ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 3/6/2025 Conditional Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Partial Approval LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 4/21/2025 Approved LILIANA PORTILLO
Gas Test 4/21/2025 Approved LILIANA PORTILLO
HVAC-Rough 4/21/2025 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 4/21/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 4/22/2025 Conditional Approval LILIANA PORTILLO
HVAC-Rough 4/22/2025 Approved LILIANA PORTILLO
Insulation 4/28/2025 Conditional Approval LILIANA PORTILLO
Interior/Exterior Lathing 4/28/2025 Not Ready for Inspection LILIANA PORTILLO
Shower Pan 4/28/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 5/1/2025 Approved ALEX COLIN
Drywall Nailing 5/6/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 12/5/2025 Not Ready for Inspection LILIANA PORTILLO
Final 12/5/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 12/5/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 12/5/2025 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 12/5/2025 Not Ready for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 12/18/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 12/18/2025 Not Ready for Inspection LILIANA PORTILLO
Final 12/18/2025 Not Ready for Inspection LILIANA PORTILLO
Footing/Foundation/Slab 12/18/2025 Approved LILIANA PORTILLO
HVAC-Final 12/18/2025 Approved LILIANA PORTILLO
MERV13>=Final 12/18/2025 Approved LILIANA PORTILLO
MERV13>=Rough 12/18/2025 Approved LILIANA PORTILLO
PLUMBING-Final 12/18/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/18/2025 SGSOV Approved LILIANA PORTILLO
Service/Power Release 12/18/2025 Not Ready for Inspection LILIANA PORTILLO
Smoke Detectors 12/18/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 2/12/2026 Approved LILIANA PORTILLO
Final 2/12/2026 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 2/12/2026 Approved LILIANA PORTILLO
Final 5/22/2026 OK to Issue CofO LILIANA PORTILLO