2671 S ANCHOR AVE 90064

Certificate Information: 2671 S ANCHOR AVE 90064

Application / Permit
25014-10000-00076
Plan Check / Job No.
B24LA38377
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan - ADDITION AND MAJOR REMODEL TO EXISTING SFD W GARAGE
Permit Issued
Issued on 5/28/2025
Issuing Office
Current Status
Issued on 5/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/10/2025 APPLICANT
Assigned to Plan Check Engineer 1/16/2025 STARR CHEN
Corrections Issued 1/23/2025 STARR CHEN
Quality Review Completed 1/23/2025 EUGENE BARBEAU
Applicant returned to address corrections 4/11/2025 STARR CHEN
Applicant returned to address corrections 4/15/2025 STARR CHEN
Applicant returned to address corrections 4/25/2025 STARR CHEN
Plan Check Approved 5/9/2025 STARR CHEN
Plan Check Approved 5/28/2025 STARR CHEN
Issued 5/28/2025 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/6/2025 LIAM ODONOVAN
Sewer availability Cleared 2/6/2025 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 2/10/2025 LIAM ODONOVAN
Hydrant and Access approval Cleared 2/12/2025 KURT CORRAL
Trees in Parkway Cleared 2/27/2025 RICHARD SANCHEZ
Permit Cleared 2/28/2025 LIAM ODONOVAN
Specific Plan Cleared 4/1/2025 RICHARD WOO
Grading Pre-Inspection Cleared 4/25/2025 STARR CHEN
GPI Written Notices Cleared 5/7/2025 STARR CHEN

Contact Information

Contractor Owner-Builder       ,
Engineer Onishi,, Robert K; Lic. No.: S3705 4438 LINDBLADE DRIVE      LOS ANGELES, CA 90066
Geologist Kaligi,, Adam Azad; Lic. No.: GEO9287 19197 GOLDEN VALLEY RD #709      SANTA CLARITA, CA 91387

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/9/2025 Partial Approval EVAN COOPER
METHANE-Barrier 6/9/2025 Not Ready for Inspection EVAN COOPER
METHANE-Rough 6/9/2025 Partial Approval EVAN COOPER
METHANE-Subgrade 6/9/2025 Partial Approval EVAN COOPER
PLUMBING-Rough 6/9/2025 Partial Approval EVAN COOPER
METHANE-Subgrade 6/17/2025 Approved ASHLEY THOMPSON
METHANE-Rough 8/6/2025 Partial Approval EVAN COOPER
Deputy Methane Barrier 8/20/2025 Conditional Approval MICHAEL PELHAM
Deputy Methane Barrier 8/21/2025 Conditional Approval MICHAEL PELHAM
Deputy Methane Barrier 8/22/2025 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 8/29/2025 Approved ASHLEY THOMPSON
METHANE-Barrier 8/29/2025 Approved ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 11/12/2025 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 12/31/2025 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Rough 12/31/2025 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 12/31/2025 Corrections Issued ASHLEY THOMPSON
METHANE-Rough 12/31/2025 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 12/31/2025 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 1/20/2026 Partial Approval ASHLEY THOMPSON
ELECTRICAL-Rough 1/20/2026 Approved ASHLEY THOMPSON
HVAC-Rough 1/20/2026 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 1/20/2026 Partial Approval ASHLEY THOMPSON
METHANE-Rough 1/20/2026 Approved ASHLEY THOMPSON
PLUMBING-Rough 1/20/2026 Approved ASHLEY THOMPSON
Wood Frame 1/20/2026 Partial Approval ASHLEY THOMPSON
Insulation 1/26/2026 Corrections Issued ASHLEY THOMPSON
Interior/Exterior Lathing 1/26/2026 Partial Approval ASHLEY THOMPSON
Insulation 1/28/2026 Approved WILBER ROSALES
BUILDING-Rough-Frame 3/6/2026 Corrections Issued ASHLEY THOMPSON
Drywall Nailing 3/16/2026 Partial Approval ASHLEY THOMPSON
Shower Pan 3/16/2026 Not Ready for Inspection ASHLEY THOMPSON
Shower Pan 4/8/2026 Approved ASHLEY THOMPSON
METHANE-Barrier 4/21/2026 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 5/7/2026 Approved ASHLEY THOMPSON