4250 W 59TH ST 90043
Certificate Information: 4250 W 59TH ST 90043
- Application / Permit
- 25014-10000-00068
- Plan Check / Job No.
- B25LA00437
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION TO ADU AND ADU ADDITION TO CREATE A TWO STORY ADU
- Permit Issued
- Issued on 5/14/2025
- Issuing Office
- Metro
- Current Status
- Issued on 5/14/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/7/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2025 | ARSALAN SHABESTARI |
| Corrections Issued | 1/21/2025 | ARSALAN SHABESTARI |
| Quality Review Completed | 2/14/2025 | KEN GILL |
| Building Plans Picked Up | 2/14/2025 | APPLICANT |
| Plan Check Approved | 5/14/2025 | ARSALAN SHABESTARI |
| Issued | 5/14/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/20/2025 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/20/2025 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 2/20/2025 | WALLIE JONG |
| Construction near power lines | Cleared | 3/28/2025 | TINA MIRANDA |
| Construction within easement | Cleared | 3/28/2025 | TINA MIRANDA |
| GPI Written Notices | Cleared | 4/24/2025 | ARSALAN SHABESTARI |
| Grading Pre-Inspection | Cleared | 4/24/2025 | ARSALAN SHABESTARI |
| Sewer availability | Cleared | 4/25/2025 | DAVID VO |
Contact Information
| Contractor | Cavalier Builders Inc; Lic. No.: 758563-B | 7106 OWENSMOUTH AVE CANOGA PARK, CA 91303 |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/20/2025 | Corrections Issued | WAYNE REGESTER |
| Footing/Foundation/Slab | 7/3/2025 | Approved | WAYNE REGESTER |
| METHANE-Barrier | 7/3/2025 | Approved | WAYNE REGESTER |
| METHANE-Subgrade | 7/3/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 7/3/2025 | Partial Approval | WAYNE REGESTER |
| Excavation/Setback/Form/Re-Bar | 7/8/2025 | Approved | WAYNE REGESTER |
| PLUMBING-Rough | 7/8/2025 | Partial Approval | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2025 | Partial Approval | WAYNE REGESTER |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 9/3/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2025 | Corrections Issued | BARRY HACHE |
| Sewer | 9/17/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 10/1/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 10/3/2025 | Corrections Issued | BARRY HACHE |
| Deputy Drilled-In Anchors | 10/6/2025 | Conditional Approval | RONNIE MEDINA |
| ELECTRICAL-Rough | 10/7/2025 | Conditional Approval | SALVADOR MARTINEZ |
| HVAC-Rough | 10/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 10/7/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 10/14/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Rough | 10/14/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2025 | Approved | LUIS CASTRO |
| Green Building Rough | 10/14/2025 | Not Ready for Inspection | LUIS CASTRO |
| HVAC-Rough | 10/14/2025 | Corrections Issued | LUIS CASTRO |
| Insulation | 10/14/2025 | Partial Approval | LUIS CASTRO |
| METHANE-Rough | 10/14/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 10/14/2025 | Corrections Issued | LUIS CASTRO |
| Underground Mechanical | 10/14/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Rough | 10/28/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 10/31/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 10/31/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Rough | 10/31/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 10/31/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| METHANE-Rough | 10/31/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/31/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 11/6/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 11/6/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 11/6/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 11/6/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 11/6/2025 | Partial Approval | SALVADOR MARTINEZ |
| METHANE-Rough | 11/6/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 11/6/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 11/12/2025 | Partial Approval | SALVADOR MARTINEZ |
| Insulation | 11/12/2025 | Partial Approval | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 11/12/2025 | Partial Approval | SALVADOR MARTINEZ |
| Shower Pan | 11/13/2025 | Approved | DEVON JACKSON |
| Drywall Nailing | 11/24/2025 | Approved | DEVON JACKSON |
| Insulation | 11/24/2025 | Approved | DEVON JACKSON |
| Interior/Exterior Lathing | 11/26/2025 | Approved | ALEX COLIN |
| BUILDING-Rough-Frame | 2/25/2026 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 2/25/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 2/25/2026 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 2/25/2026 | Conditional Approval | SALVADOR MARTINEZ |
| HVAC-Final | 2/25/2026 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 2/25/2026 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 2/25/2026 | SGSOV No Gas | SALVADOR MARTINEZ |
| Smoke Detectors | 2/25/2026 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/6/2026 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 4/6/2026 | Approved | SABAS ALONSO |
| Final | 4/6/2026 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 4/6/2026 | Approved | SABAS ALONSO |
| HVAC-Final | 4/6/2026 | Approved | SABAS ALONSO |
| PLUMBING-Final | 4/6/2026 | Approved | SABAS ALONSO |