4340 S 2ND AVE 90008

Certificate Information: 4340 S 2ND AVE 90008

Application / Permit
25014-10000-00059
Plan Check / Job No.
B25LA00358
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO CREATE NEW BATHROOM AND WALK IN CLOSET, BATHROOM AND KITCHEN REMODEL AT (E) SFD. WORK PER WFPP.
Permit Issued
Issued on 1/22/2025
Issuing Office
Metro
Current Status
CofO Issued on 1/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2025 APPLICANT
Assigned to Plan Check Engineer 1/8/2025 EDWIN MARTINEZ
Corrections Issued 1/9/2025 EDWIN MARTINEZ
Building Plans Picked Up 1/14/2025 APPLICANT
Plan Check Approved 1/21/2025 MINA HABILI
Issued 1/22/2025 APPLICANT
CofO in Progress 1/15/2026 LUIS CASTRO
Permit Finaled 1/16/2026 DEROLD HAUFF
CofO Issued 1/16/2026 DEROLD HAUFF
Permit Finaled 1/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/18/2025 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/18/2025 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/24/2025 Approved LUIS CASTRO
Footing/Foundation/Slab 2/24/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 3/17/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 3/17/2025 Partial Approval LUIS CASTRO
Sewer 3/17/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 4/18/2025 Corrections Issued LUIS CASTRO
ELECTRICAL-Rough 4/18/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 4/18/2025 Corrections Issued LUIS CASTRO
HVAC-Rough 4/18/2025 Partial Approval LUIS CASTRO
PLUMBING-Rough 4/18/2025 Corrections Issued LUIS CASTRO
Excavation/Setback/Form/Re-Bar 5/6/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Approved LUIS CASTRO
PLUMBING-Rough 5/6/2025 Approved LUIS CASTRO
Deputy Drilled-In Anchors 5/7/2025 Approved LUIS CASTRO
BUILDING-Rough-Frame 5/8/2025 Conditional Approval LUIS CASTRO
ELECTRICAL-Rough 5/8/2025 Approved LUIS CASTRO
Green Building Rough 5/8/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 5/8/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 5/8/2025 Partial Approval LUIS CASTRO
Interior/Exterior Lathing 5/16/2025 Partial Approval LUIS CASTRO
Insulation 5/19/2025 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 12/11/2025 Approved LUIS CASTRO
Drywall Nailing 12/11/2025 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Final 12/11/2025 Approved LUIS CASTRO
Final 12/11/2025 Corrections Issued LUIS CASTRO
Green Building Final 12/11/2025 Not Ready for Inspection LUIS CASTRO
Green Building Rough 12/11/2025 Approved LUIS CASTRO
HVAC-Final 12/11/2025 Approved LUIS CASTRO
PLUMBING-Final 12/11/2025 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Approved LUIS CASTRO
Smoke Detectors 12/11/2025 Approved LUIS CASTRO
Drywall Nailing 1/5/2026 Approved LUIS CASTRO
Final 1/5/2026 Corrections Issued LUIS CASTRO
Green Building Final 1/5/2026 Not Ready for Inspection LUIS CASTRO
Final 1/9/2026 Not Ready for Inspection LUIS CASTRO
Green Building Final 1/9/2026 Not Ready for Inspection LUIS CASTRO
Final 1/15/2026 OK to Issue CofO LUIS CASTRO
Green Building Final 1/15/2026 Approved LUIS CASTRO
Service/Power Release 1/15/2026 Approved LUIS CASTRO