244-244 1/2 E 97TH ST 90003

Certificate Information: 244-244 1/2 E 97TH ST 90003

Application / Permit
25014-10000-00046
Plan Check / Job No.
B25LA00276
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
MAJOR REMODEL AND ADDITION TO EXISTING 1-STORY SINGLE FAMILY DWELLING TO BECOME A DUPLEX
Permit Issued
Issued on 3/6/2025
Issuing Office
Metro
Current Status
CofO Issued on 1/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/6/2025 APPLICANT
Assigned to Plan Check Engineer 1/9/2025 JAD BASMA
Corrections Issued 1/12/2025 JAD BASMA
Quality Review Completed 1/14/2025 KEN GILL
Building Plans Picked Up 1/17/2025 APPLICANT
Plan Check Approved 3/6/2025 JAD BASMA
Issued 3/6/2025 APPLICANT
CofO in Progress 1/26/2026 ANSON MAGLASANG
Permit Finaled 1/26/2026 ANSON MAGLASANG
CofO Issued 1/26/2026 ANSON MAGLASANG
Permit Finaled 1/26/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/16/2025 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/16/2025 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 1/16/2025 ADRIAN SANCHEZ
Sewer availability Cleared 1/22/2025 CHRISTINA BRACO

Contact Information

Contractor So Cal Construction Enterprises Inc; Lic. No.: 832488-B P O BOX 96      SAN GABRIEL, CA 91778

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/21/2025 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 3/21/2025 Corrections Issued ANTHONY EGSON
Deputy Drilled-In Anchors 3/24/2025 Approved BEN MOLSTAD
Excavation/Setback/Form/Re-Bar 3/25/2025 Approved BEN MOLSTAD
Sewer 3/25/2025 Partial Approval BEN MOLSTAD
BUILDING-Rough-Frame 4/2/2025 Partial Approval BEN MOLSTAD
Floor/Roof Diaphrgm/Shear Wall 4/2/2025 Not Ready for Inspection BEN MOLSTAD
Insulation 4/4/2025 Partial Approval ANTHONY EGSON
PLUMBING-Rough 4/4/2025 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/7/2025 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 4/18/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 4/18/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 4/18/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 4/22/2025 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/22/2025 Approved ANTHONY EGSON
Green Building Rough 4/22/2025 Approved ANTHONY EGSON
HVAC-Rough 4/22/2025 Partial Approval ANTHONY EGSON
Insulation 4/28/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 4/28/2025 Approved ANTHONY EGSON
Interior/Exterior Lathing 5/1/2025 Not Ready for Inspection ANTHONY EGSON
Drywall Nailing 5/2/2025 Approved BEN MOLSTAD
Interior/Exterior Lathing 5/6/2025 Approved ANTHONY EGSON
ELECTRICAL-Final 9/8/2025 Approved JOSEPH MCGARRY
Gas Test 9/8/2025 Approved JOSEPH MCGARRY
HVAC-Final 9/8/2025 Approved JOSEPH MCGARRY
PLUMBING-Final 9/8/2025 Corrections Issued JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 9/8/2025 SGSOV Not Ready JOSEPH MCGARRY
Smoke Detectors 9/8/2025 Approved JOSEPH MCGARRY
Special/Order Compliance 9/8/2025 Corrections Issued JOSEPH MCGARRY
BUILDING-Rough-Frame 10/17/2025 Approved ANTHONY EGSON
Final 10/17/2025 OK to Issue CofO ANTHONY EGSON
Footing/Foundation/Slab 10/17/2025 Approved ANTHONY EGSON
Green Building Final 10/17/2025 Approved ANTHONY EGSON
Green Building Rough 10/17/2025 Approved ANTHONY EGSON
PLUMBING-Final 10/17/2025 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 10/17/2025 SGSOV Not Required ANTHONY EGSON