14647-14649 W MORRISON ST 91403

Certificate Information: 14647-14649 W MORRISON ST 91403

Application / Permit
25014-10000-00022
Plan Check / Job No.
B24LA38286
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: Major remodel and addition to (e) one-story sfd Convert attached garage to JADU per state law Work per engineer ***13D SPRINKLER REQUIRED***
Permit Issued
Issued on 5/19/2025
Issuing Office
Current Status
CofO Issued on 2/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2025 APPLICANT
Assigned to Plan Check Engineer 1/9/2025 KHUONG TRUONG
Corrections Issued 1/14/2025 KHUONG TRUONG
Quality Review Completed 1/16/2025 GARO TELMI
Plan Check Approved 5/15/2025 KHUONG TRUONG
Issued 5/19/2025 APPLICANT
CofO in Progress 1/12/2026 JACK KARGODORIAN
No Progress 1/27/2026 RAUL OLAGI
CofO in Progress 1/27/2026 RAUL OLAGI
Permit Finaled 2/3/2026 RUBEN SALAS
CofO Issued 2/3/2026 RUBEN SALAS
Permit Finaled 2/3/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/21/2025 RYAN CASTRO
Roof/Waste drainage to street Cleared 1/21/2025 RYAN CASTRO
Sewer availability Cleared 1/21/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/6/2025 BIAINA HARITUNIAN
ZI Cleared 3/16/2025 JAZMIN ROQUE

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/5/2025 Corrections Issued JACK KARGODORIAN
Excavation/Setback/Form/Re-Bar 6/6/2025 Approved JACK KARGODORIAN
Underground Mechanical 6/18/2025 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Partial Approval JACK KARGODORIAN
Deputy Wood Construction 6/24/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 7/18/2025 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 7/21/2025 Corrections Issued JACK KARGODORIAN
Deputy Drilled-In Anchors 7/22/2025 Conditional Approval JUAN VALENZUELA
Deputy Wood Construction 7/22/2025 Conditional Approval JUAN VALENZUELA
Wood Frame 7/22/2025 Partial Approval JACK KARGODORIAN
PLUMBING-Rough 7/25/2025 Approved JACK KARGODORIAN
ELECTRICAL-Rough 8/5/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 8/5/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 8/11/2025 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 8/11/2025 Partial Approval JAVIER RAMOS JR
Pre-Inspection 8/11/2025 Approved JAVIER RAMOS JR
Wood Frame 8/11/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 8/12/2025 No Access for Inspection MISAEL ESPARZA
Insulation 8/12/2025 No Access for Inspection MISAEL ESPARZA
Wood Frame 8/12/2025 No Access for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 8/14/2025 Approved JACK KARGODORIAN
Insulation 8/14/2025 Approved JACK KARGODORIAN
Wood Frame 8/14/2025 Approved JACK KARGODORIAN
Shower Pan 8/18/2025 Approved JACK KARGODORIAN
Drywall Nailing 8/20/2025 Partial Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 8/20/2025 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 8/20/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/6/2026 Approved JACK KARGODORIAN
ELECTRICAL-Final 1/6/2026 Corrections Issued JACK KARGODORIAN
Final 1/6/2026 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 1/6/2026 Approved JACK KARGODORIAN
Green Building Final 1/6/2026 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 1/6/2026 Approved JACK KARGODORIAN
HVAC-Final 1/6/2026 Approved JACK KARGODORIAN
MERV13>=Final 1/6/2026 Approved JACK KARGODORIAN
MERV13>=Rough 1/6/2026 Approved JACK KARGODORIAN
PLUMBING-Final 1/6/2026 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 1/6/2026 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 1/6/2026 Approved JACK KARGODORIAN
ELECTRICAL-Final 1/9/2026 Approved JACK KARGODORIAN
Final 1/9/2026 OK to Issue CofO JACK KARGODORIAN
Green Building Final 1/9/2026 Approved JACK KARGODORIAN
HVAC-Final 1/9/2026 Approved JACK KARGODORIAN
PLUMBING-Final 1/9/2026 Approved JACK KARGODORIAN
Service/Power Release 1/9/2026 Approved JACK KARGODORIAN