582 N LILLIAN WAY 90004
Certificate Information: 582 N LILLIAN WAY 90004
- Application / Permit
- 25014-10000-00010
- Plan Check / Job No.
- B24LA38252
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF EXISTING DETACHED GARAGE AND NEW ADDITION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33(c) AND (d). NEW COVERED ENTRY PORCH. RE-FRAME ROOF OF THE STRUCTURE. PORTION OF EXISTING GARAGE TO BE REMOVED. WORK DONE PER ENGINEER DESIGN. Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2).
- Permit Issued
- Issued on 4/29/2025
- Issuing Office
- Current Status
- Issued on 4/29/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2025 | MADISON ODELL |
| Corrections Issued | 1/7/2025 | MADISON ODELL |
| Applicant returned to address corrections | 3/24/2025 | MADISON ODELL |
| Applicant returned to address corrections | 4/9/2025 | MADISON ODELL |
| Plan Check Approved | 4/25/2025 | MADISON O'DELL |
| Issued | 4/29/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/23/2025 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 1/23/2025 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2025 | TREVOR QUAN |
| Sewer availability | Cleared | 1/24/2025 | TREVOR QUAN |
| CPC | Cleared | 1/29/2025 | SUKI GERSHENHORN |
| HPOZ | Cleared | 1/29/2025 | SUKI GERSHENHORN |
| Flood clearance | Cleared | 1/31/2025 | TUYEN LE |
| Construction near power lines | Cleared | 2/21/2025 | RIDWAN HARDY |
| Miscellaneous | Cleared | 3/19/2025 | ALBERT TAM |
Contact Information
| Architect | Pickhardt,, Mary; Lic. No.: NA25772 | , |
| Contractor | Shanks Construction; Lic. No.: 707647-B | , |
| Engineer | Ekmekji,, Steve Eli; Lic. No.: NA66727 | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/2/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 6/4/2025 | Approved | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 6/17/2025 | Conditional Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2025 | Partial Approval | JEFFREY MEAD |
| Underground Mechanical | 9/4/2025 | Partial Approval | JEFFREY MEAD |
| Gas Test | 9/15/2025 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 9/15/2025 | Approved | JEFFREY MEAD |
| Sewer | 9/15/2025 | Approved | JEFFREY MEAD |
| Underground Mechanical | 9/15/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/9/2025 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/9/2025 | Approved | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2025 | Partial Approval | JEFFREY MEAD |
| Green Building Rough | 10/9/2025 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 10/9/2025 | Approved | JEFFREY MEAD |
| METHANE-Rough | 10/9/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 10/28/2025 | Partial Approval | JEFFREY MEAD |
| Shower Pan | 11/6/2025 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 11/13/2025 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 12/15/2025 | Approved | JEFFREY MEAD |
| Green Building Rough | 12/15/2025 | Approved | JEFFREY MEAD |
| Insulation | 12/19/2025 | Approved | JEFFREY MEAD |
| Drywall Nailing | 2/17/2026 | Approved | JEFFREY MEAD |