8313 S STEWART AVE 90045

Certificate Information: 8313 S STEWART AVE 90045

Application / Permit
25010-70000-02645
Plan Check / Job No.
B25SL00630
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New two story single family dwelling with attached garage.
Permit Issued
Issued on 8/29/2025
Issuing Office
Metro
Current Status
Issued on 8/29/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/12/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 ARSALAN SHABESTARI
Assigned to Zoning Architect 6/20/2025 VAHE ZARUKIAN
Corrections Issued 7/1/2025 ARSALAN SHABESTARI
Quality Review Completed 7/3/2025 KEN GILL
Building Plans Picked Up 7/7/2025 APPLICANT
Plan Check Approved 8/26/2025 ARSALAN SHABESTARI
Issued 8/29/2025 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 7/9/2025 KURT CORRAL
Address approval Cleared 7/14/2025 DERRICK MAGEE
Roof/Waste drainage to street Cleared 7/14/2025 DERRICK MAGEE
Sewer availability Cleared 7/14/2025 DERRICK MAGEE
Eng Process Fee Ord 176,300 Cleared 7/15/2025 DERRICK MAGEE
CPC Cleared 7/18/2025 DAVID URITA
CPC Cleared 7/18/2025 DAVID URITA
CPC Cleared 7/18/2025 DAVID URITA
Frnt yard landscape/Water mgmt Cleared 7/18/2025 DAVID URITA
Trees in Parkway Cleared 8/8/2025 MIGUEL ORNELAS
Permit Cleared 8/11/2025 DERRICK MAGEE
Specific Plan Cleared 8/15/2025 PEDRO AYALA
Zoning Plan Check Cleared 8/21/2025 VAHEN ZAKURIAN

Contact Information

Contractor Tosty'S Construction; Lic. No.: 550499-B 3455 CATTARAUGUS AVE      CULVER CITY, CA 90232

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 9/5/2025 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 9/5/2025 Partial Approval JESUS PINEDA
Deputy Reinf. Concrete 9/8/2025 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/24/2025 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 9/24/2025 Approved JESUS PINEDA
PLUMBING-Rough 9/24/2025 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 9/29/2025 Partial Approval JESUS PINEDA
Insulation 9/29/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 12/8/2025 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Conditional Approval BOBBY KEY
Special/Order Compliance 12/8/2025 Partial Inspection HERBERT GIRON
Special/Order Compliance 12/8/2025 Partial Inspection TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 12/30/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 2/5/2026 Conditional Approval JESUS PINEDA
PLUMBING-Rough 2/17/2026 Corrections Issued JESUS PINEDA
PLUMBING-Rough 3/2/2026 Approved JESUS PINEDA
Sewer 3/2/2026 Approved JESUS PINEDA
Underground Mechanical 3/2/2026 Partial Approval JESUS PINEDA
HVAC-Rough 3/13/2026 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 3/26/2026 Approved JESUS PINEDA
Interior/Exterior Lathing 3/26/2026 Partial Approval JESUS PINEDA
HVAC-Rough 3/27/2026 Approved JESUS PINEDA
BUILDING-Rough-Frame 4/2/2026 Approved JESUS PINEDA
Final 4/2/2026 Corrections Issued JESUS PINEDA
Green Building Rough 4/2/2026 Approved JESUS PINEDA
Verify Sprinkler Sign Off 4/2/2026 Approved JESUS PINEDA
Insulation 4/21/2026 Approved DAVID FEILER
Drywall Nailing 6/1/2026 Approved MICHAEL LEWIS
Interior/Exterior Lathing 6/1/2026 Approved MICHAEL LEWIS
Shower Pan 6/1/2026 Approved MICHAEL LEWIS