831 E 101ST ST 90002

Certificate Information: 831 E 101ST ST 90002

Application / Permit
25010-70000-02416
Plan Check / Job No.
B25SL00577
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached one story ADU PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k).
Permit Issued
Issued on 7/29/2025
Issuing Office
South Los Angeles
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/29/2025 APPLICANT
Assigned to Plan Check Engineer 6/3/2025 RICARDO RAMIREZ
Corrections Issued 6/4/2025 RICARDO RAMIREZ
Issued 7/29/2025 APPLICANT
CofO in Progress 2/5/2026 ARTHUR NEGRETE
Permit Finaled 3/10/2026 ANSON MAGLASANG
CofO Issued 3/10/2026 ANSON MAGLASANG
Permit Finaled 3/10/2026 ANSON MAGLASANG

Permit Application Clearance Information

Construction near power lines Cleared 7/21/2025 RIDWAN HARDY
Address approval Cleared 7/24/2025 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 7/24/2025 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 7/28/2025 LEE GUILBEAUX
Sewer availability Cleared 7/28/2025 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/16/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 9/16/2025 Corrections Issued ANTHONY EGSON
Excavation/Setback/Form/Re-Bar 9/19/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 9/19/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 9/19/2025 Approved ANTHONY EGSON
Footing/Foundation/Slab 9/23/2025 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 10/17/2025 Approved ANTHONY EGSON
BUILDING-Rough-Frame 10/29/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 10/29/2025 Partial Approval ANTHONY EGSON
Green Building Rough 10/29/2025 Approved ANTHONY EGSON
PLUMBING-Rough 10/29/2025 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 11/3/2025 Approved ANTHONY EGSON
Insulation 11/3/2025 Corrections Issued ANTHONY EGSON
Drywall Nailing 11/13/2025 Not Ready for Inspection ANTHONY EGSON
Interior/Exterior Lathing 11/13/2025 Approved ANTHONY EGSON
Drywall Nailing 1/28/2026 Approved ARTHUR NEGRETE
ELECTRICAL-Final 1/28/2026 Approved ARTHUR NEGRETE
Final 1/28/2026 Not Ready for Inspection ARTHUR NEGRETE
Green Building Final 1/28/2026 Not Ready for Inspection ARTHUR NEGRETE
HVAC-Final 1/28/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 1/28/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 1/28/2026 SGSOV Not Required ARTHUR NEGRETE
Service/Power Release 1/28/2026 Not Ready for Inspection ARTHUR NEGRETE
Smoke Detectors 1/28/2026 Approved ARTHUR NEGRETE
Final 2/4/2026 OK to Issue CofO ARTHUR NEGRETE
Green Building Final 2/4/2026 Approved ARTHUR NEGRETE
Service/Power Release 2/4/2026 Approved ARTHUR NEGRETE