831 E 101ST ST 90002
Certificate Information: 831 E 101ST ST 90002
- Application / Permit
- 25010-70000-02416
- Plan Check / Job No.
- B25SL00577
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached one story ADU PER LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k).
- Permit Issued
- Issued on 7/29/2025
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 3/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2025 | RICARDO RAMIREZ |
| Corrections Issued | 6/4/2025 | RICARDO RAMIREZ |
| Issued | 7/29/2025 | APPLICANT |
| CofO in Progress | 2/5/2026 | ARTHUR NEGRETE |
| Permit Finaled | 3/10/2026 | ANSON MAGLASANG |
| CofO Issued | 3/10/2026 | ANSON MAGLASANG |
| Permit Finaled | 3/10/2026 | ANSON MAGLASANG |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/21/2025 | RIDWAN HARDY |
| Address approval | Cleared | 7/24/2025 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/24/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/28/2025 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/16/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 9/16/2025 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 9/19/2025 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/19/2025 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 9/19/2025 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 9/23/2025 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/29/2025 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/29/2025 | Partial Approval | ANTHONY EGSON |
| Green Building Rough | 10/29/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 10/29/2025 | Partial Approval | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/3/2025 | Approved | ANTHONY EGSON |
| Insulation | 11/3/2025 | Corrections Issued | ANTHONY EGSON |
| Drywall Nailing | 11/13/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/13/2025 | Approved | ANTHONY EGSON |
| Drywall Nailing | 1/28/2026 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 1/28/2026 | Approved | ARTHUR NEGRETE |
| Final | 1/28/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 1/28/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| HVAC-Final | 1/28/2026 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 1/28/2026 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 1/28/2026 | SGSOV Not Required | ARTHUR NEGRETE |
| Service/Power Release | 1/28/2026 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 1/28/2026 | Approved | ARTHUR NEGRETE |
| Final | 2/4/2026 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 2/4/2026 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 2/4/2026 | Approved | ARTHUR NEGRETE |