4321 S STEWART AVE 90066
Certificate Information: 4321 S STEWART AVE 90066
- Application / Permit
- 25010-70000-00733
- Plan Check / Job No.
- B25SL00123
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition to rear of single family dwelling to create additional bathroom and bedroom.
- Permit Issued
- Issued on 6/3/2025
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 4/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/21/2025 | RICARDO RAMIREZ |
| Corrections Issued | 2/22/2025 | RICARDO RAMIREZ |
| Building Plans Picked Up | 2/27/2025 | APPLICANT |
| Issued | 6/3/2025 | APPLICANT |
| CofO in Progress | 4/2/2026 | ANTHONY EGSON |
| Permit Finaled | 4/7/2026 | RICHARD STEINBACH |
| CofO Issued | 4/7/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/7/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/3/2025 | KIMBERLY HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 3/5/2025 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 3/11/2025 | KIMBERLY HERNANDEZ |
Contact Information
| Contractor | Dirty Girl Construction Inc; Lic. No.: 934287-B | 4321 STEWART AVENUE LOS ANGELES, CA 90066 |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/10/2025 | Approved | RUBEN RIVAS |
| Footing/Foundation/Slab | 7/10/2025 | Approved | RUBEN RIVAS |
| Underground Mechanical | 7/10/2025 | Approved | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2025 | Partial Approval | RUBEN RIVAS |
| PLUMBING-Rough | 7/28/2025 | Partial Approval | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 9/17/2025 | Corrections Issued | RUBEN RIVAS |
| ELECTRICAL-Rough | 9/17/2025 | Corrections Issued | RUBEN RIVAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2025 | Partial Approval | RUBEN RIVAS |
| Green Building Rough | 9/17/2025 | Approved | RUBEN RIVAS |
| HVAC-Rough | 9/17/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 9/17/2025 | Approved | RUBEN RIVAS |
| BUILDING-Rough-Frame | 9/25/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Rough | 9/25/2025 | Approved | RUBEN RIVAS |
| Interior/Exterior Lathing | 9/30/2025 | Approved | RUBEN RIVAS |
| Insulation | 10/6/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 10/30/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Final | 3/9/2026 | Corrections Issued | ANTHONY EGSON |
| Final | 3/9/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 3/9/2026 | Approved | ANTHONY EGSON |
| HVAC-Final | 3/9/2026 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 3/9/2026 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 3/9/2026 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 3/9/2026 | Approved | ANTHONY EGSON |
| Smoke Detectors | 3/9/2026 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 4/1/2026 | Approved | ANTHONY EGSON |
| Final | 4/1/2026 | OK to Issue CofO | ANTHONY EGSON |
| HVAC-Final | 4/1/2026 | Approved | ANTHONY EGSON |
| Smoke Detectors | 4/1/2026 | Approved | ANTHONY EGSON |