1367 W 39TH ST 90062
Certificate Information: 1367 W 39TH ST 90062
- Application / Permit
- 25010-70000-00478
- Plan Check / Job No.
- B25SL00075
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached two story ADU with attached 2-car garage and attached 1-car carport. ADU per LAMC 12.22 A.33(b)(1)(c), (d), (h), and (k)
- Permit Issued
- Issued on 7/15/2025
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 7/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 2/20/2025 | KHEDER ALRAZAA |
| Assigned to Zoning Architect | 2/25/2025 | KAREN MEZA-MORALES |
| Corrections Issued | 3/6/2025 | KHEDER ALRAZAA |
| Quality Review Completed | 3/21/2025 | KEN GILL |
| Building Plans Picked Up | 4/2/2025 | APPLICANT |
| Plan Check Approved | 7/1/2025 | KHEDER ALRAZAA |
| Issued | 7/15/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/10/2025 | CINDY QI |
| Tenant Habitability Plan | Cleared | 4/10/2025 | RICARDO BOHORQUEZ |
| Community Plan Implem. Overlay | Cleared | 4/11/2025 | BRANDON WONG |
| Roof/Waste drainage to street | Cleared | 4/11/2025 | CINDY QI |
| Community Plan Implem. Overlay | Cleared | 4/15/2025 | MANERI ROMAN |
| Community Plan Implem. Overlay | Cleared | 4/22/2025 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 4/22/2025 | JESSICA OPINION |
| Community Plan Implem. Overlay | Cleared | 6/6/2025 | RIDWAN HARDY |
| Zoning Plan Check | Cleared | 6/10/2025 | KAREN MEZA-MORALES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wong,, Jim C; Lic. No.: C69393 | 1822 E ROUTE 66, SUITE A, PO BOX 328 GLENDORA, CA 91740 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/8/2025 | Conditional Approval | RONNIE MEDINA |
| Footing/Foundation/Slab | 9/9/2025 | Approved | JOSE MACIAS |
| Wood Frame | 9/18/2025 | Corrections Issued | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 11/20/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 11/20/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 11/20/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 12/1/2025 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/1/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/8/2025 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 12/8/2025 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 12/8/2025 | Partial Approval | SABAS ALONSO |
| Verify Sprinkler Sign Off | 12/8/2025 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/15/2025 | Approved | SABAS ALONSO |
| Insulation | 12/15/2025 | Approved | SABAS ALONSO |
| Drywall Nailing | 12/18/2025 | Approved | ALEX COLIN |
| Shower Pan | 12/18/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 1/9/2026 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 1/13/2026 | Approved | SABAS ALONSO |
| Sewer | 3/26/2026 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/26/2026 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 4/3/2026 | Approved | SABAS ALONSO |