121 W 56TH ST 90037

Certificate Information: 121 W 56TH ST 90037

Application / Permit
25010-70000-00259
Plan Check / Job No.
B25SL00035
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU at rear of lot per LAMC. Framing to comply with wood frame perscriptive provisions.
Permit Issued
Issued on 2/11/2025
Issuing Office
South Los Angeles
Current Status
CofO Issued on 7/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/21/2025 APPLICANT
Assigned to Plan Check Engineer 1/21/2025 RICARDO RAMIREZ
Corrections Issued 1/25/2025 RICARDO RAMIREZ
Building Plans Picked Up 1/28/2025 APPLICANT
Plan Check Approved 2/4/2025 RICARDO RAMIREZ
Issued 2/11/2025 APPLICANT
CofO in Progress 7/15/2025 ALEJANDRO DE ARTOLA
Permit Finaled 7/16/2025 DEROLD HAUFF
CofO Issued 7/16/2025 DEROLD HAUFF
Permit Finaled 7/16/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/30/2025 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 1/30/2025 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 2/4/2025 ADRIAN SANCHEZ
Sewer availability Cleared 2/4/2025 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 3/7/2025 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/11/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 3/26/2025 Partial Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/1/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 4/1/2025 Corrections Issued BARRY HACHE
Green Building Rough 4/1/2025 Not Ready for Inspection BARRY HACHE
PLUMBING-Rough 4/1/2025 Corrections Issued BARRY HACHE
Verify Sprinkler Sign Off 4/1/2025 Not Ready for Inspection BARRY HACHE
ELECTRICAL-Rough 4/3/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/3/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Rough 4/4/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 4/4/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 4/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 4/8/2025 Approved ALEJANDRO DE ARTOLA
Insulation 4/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 4/15/2025 Approved ANTHONY RAMOS
Insulation 4/15/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 4/15/2025 Approved ANTHONY RAMOS
ELECTRICAL-Final 6/10/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 6/11/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/12/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 6/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 6/12/2025 Approved ALEJANDRO DE ARTOLA
Final 7/11/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 7/11/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Final 7/11/2025 Approved ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/11/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Smoke Detectors 7/11/2025 Approved ALEJANDRO DE ARTOLA
Final 7/14/2025 OK to Issue CofO ALEJANDRO DE ARTOLA