245 1/4-1/2 W 93RD ST 90003

Certificate Information: 245 1/4-1/2 W 93RD ST 90003

Application / Permit
25010-70000-00084
Plan Check / Job No.
B25SL00008
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Two new detached ADUs at rear of lot PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g).
Permit Issued
Issued on 4/10/2025
Issuing Office
South Los Angeles
Current Status
Issued on 4/10/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/7/2025 APPLICANT
Assigned to Plan Check Engineer 1/10/2025 RICARDO RAMIREZ
Corrections Issued 1/11/2025 RICARDO RAMIREZ
Building Plans Picked Up 1/21/2025 APPLICANT
Issued 4/10/2025 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 3/24/2025 RIDWAN HARDY
Address approval Cleared 3/26/2025 WALLIE JONG
Roof/Waste drainage to street Cleared 3/26/2025 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 3/27/2025 WALLIE JONG
Sewer availability Cleared 4/2/2025 DAVID LOPEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/28/2025 Partial Inspection JOHN QUINTANILLA
PLUMBING-Rough 10/23/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 10/27/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 10/28/2025 Approved BARRY HACHE
Excavation/Setback/Form/Re-Bar 10/31/2025 Corrections Issued JOHN QUINTANILLA
Footing/Foundation/Slab 10/31/2025 Not Ready for Inspection JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 11/3/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 11/6/2025 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 11/6/2025 Corrections Issued JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 11/7/2025 Approved JOHN QUINTANILLA
Sewer 12/1/2025 Approved DEVON JACKSON
Underground Mechanical 12/8/2025 Approved BARRY HACHE
ELECTRICAL-Rough 12/24/2025 No Access for Inspection JOHN QUINTANILLA
PLUMBING-Rough 12/24/2025 No Access for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 12/29/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 12/29/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 1/20/2026 Approved JOHN QUINTANILLA
HVAC-Rough 1/20/2026 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 1/22/2026 Conditional Approval JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 1/22/2026 Approved JOHN QUINTANILLA
Green Building Rough 1/22/2026 Not Ready for Inspection JOHN QUINTANILLA
MERV13>=Rough 1/22/2026 Approved JOHN QUINTANILLA
Verify Sprinkler Sign Off 1/22/2026 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 2/3/2026 Corrections Issued JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 2/5/2026 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 2/19/2026 Not Ready for Inspection JOHN QUINTANILLA
Insulation 2/19/2026 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 2/19/2026 Not Ready for Inspection JOHN QUINTANILLA
Drywall Nailing 2/23/2026 Corrections Issued JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 2/23/2026 Partial Inspection JOHN QUINTANILLA
Interior/Exterior Lathing 2/23/2026 Approved JOHN QUINTANILLA
Drywall Nailing 2/25/2026 Not Ready for Inspection JOHN QUINTANILLA
Insulation 2/25/2026 Not Ready for Inspection JOHN QUINTANILLA
Special/Order Compliance 2/25/2026 Not Ready for Inspection JOHN QUINTANILLA
Drywall Nailing 2/26/2026 Not Ready for Inspection JOHN QUINTANILLA
Insulation 2/26/2026 Partial Inspection JOHN QUINTANILLA
Special/Order Compliance 2/26/2026 Partial Inspection JOHN QUINTANILLA
Drywall Nailing 3/2/2026 Partial Approval ALEX COLIN
Insulation 3/2/2026 Approved ALEX COLIN
Special/Order Compliance 3/2/2026 Approved ALEX COLIN
Drywall Nailing 3/5/2026 Approved STUART CHAPMAN
Pre-Inspection 4/28/2026 Partial Inspection JOHN QUINTANILLA
Special/Order Compliance 4/28/2026 Partial Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 6/4/2026 Corrections Issued JOHN QUINTANILLA
Underground Mechanical 6/4/2026 Approved JOHN QUINTANILLA
ELECTRICAL-Final 6/25/2026 Approved ALIZAH MAYAGOITIA
HVAC-Final 6/25/2026 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 6/25/2026 Approved ALIZAH MAYAGOITIA