14910 W SUNSET BLVD 90272
Certificate Information: 14910 W SUNSET BLVD 90272
- Application / Permit
- 25010-30000-06389
- Plan Check / Job No.
- B25WL09664
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND PATIO COVER, 1-STORY, 50' x 63.83'. NFPA 13D SPRINKLERS THROUGHOUT. INELIGIBLE PROJECT.
- Permit Issued
- Issued on 2/13/2026
- Issuing Office
- Current Status
- Issued on 2/13/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2025 | MADISON ODELL |
| Corrections Issued | 1/6/2026 | MADISON ODELL |
| Quality Review Completed | 1/20/2026 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 2/13/2026 | MADISON ODELL |
| Plan Check Approved | 2/13/2026 | MADISON O'DELL |
| Issued | 2/13/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2026 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2026 | DAVID LOPEZ |
| Permit | Cleared | 1/6/2026 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 1/6/2026 | DAVID LOPEZ |
| Sewer availability | Cleared | 1/6/2026 | DAVID LOPEZ |
| Trees in Parkway | Cleared | 1/22/2026 | MIGUEL ORNELAS |
| Low Impact Development (LID) | Cleared | 1/23/2026 | MARTIN FRAGOSO |
| Hydrant and Access approval | Cleared | 1/27/2026 | PATRICK PEREZ |
| Grading Pre-Inspection | Cleared | 2/13/2026 | MADISON O'DELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boucher,, Aaron Robert; Lic. No.: C89941 | 784 WESLEYAN BAY COSTA MESA, CA 92626 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/6/2026 | Approved | MEL KHACHATOURIAN |
| Sewer | 5/8/2026 | Approved | MICHAEL ALLEN |
| Underground Mechanical | 5/8/2026 | Approved | MICHAEL ALLEN |
| Excavation/Setback/Form/Re-Bar | 6/2/2026 | Partial Approval | JESUS PINEDA |
| Footing/Foundation/Slab | 6/2/2026 | Partial Approval | JESUS PINEDA |