861 N ALMA REAL DR 90272
Certificate Information: 861 N ALMA REAL DR 90272
- Application / Permit
- 25010-30000-06109
- Plan Check / Job No.
- B25WL09538
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (16) Library non-profit
- Work Description
- ***2025 Eligible Wildfire Project Per Executive Order No. 1*** New Library; State Approved Modular Building 36'x60' on state approved temporary foundation [SEE COMMENTS] TEMPORARY FOR 2 YEARS --- 1 of 2 ---
- Permit Issued
- Issued on 1/29/2026
- Issuing Office
- Metro
- Current Status
- Issued on 1/29/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/16/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2025 | EDWIN ESPIN |
| Corrections Issued | 12/23/2025 | EDWIN ESPIN |
| Quality Review Completed | 12/23/2025 | SERGIO SILVA |
| Building Plans Picked Up | 1/21/2026 | APPLICANT |
| Applicant returned to address corrections | 1/27/2026 | EDWIN ESPIN |
| Plan Check Approved | 1/28/2026 | EDWIN ESPIN |
| Issued | 1/29/2026 | APPLICANT |
| TCO Issued (Expire Date: 07-29-2026) | 1/30/2026 | TED RIES |
| TCO Issued (Expire Date: 01-18-2027) | 7/22/2026 | TED RIES |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2026 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2026 | CINDY QI |
| Permit | Cleared | 1/5/2026 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 1/5/2026 | CINDY QI |
| Sewer availability | Cleared | 1/5/2026 | CINDY QI |
| Miscellaneous | Cleared | 1/8/2026 | YINGSHI HUANG |
| Miscellaneous | Cleared | 1/8/2026 | YINGSHI HUANG |
| City owned building/parcel | Cleared | 1/26/2026 | MASON NG |
| Low Impact Development (LID) | Cleared | 1/26/2026 | ORVAL HERNANDEZ-MARCI |
| Miscellaneous | Cleared | 1/26/2026 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 1/26/2026 | RUBEN VASQUEZ |
| Watercourse | Cleared | 1/26/2026 | HISASHI KOBAYAKAWA |
| GPI Written Notices | Cleared | 1/27/2026 | EDWIN ESPIN |
| Green Code | Cleared | 1/27/2026 | EDWIN ESPIN |
| Hydrant and Access approval | Cleared | 1/27/2026 | LAVEON RIDER |
| DAS Clearance | Cleared | 1/28/2026 | EDWIN ESPIN |
Contact Information
| Architect | Pilikyan,, Khachik C; Lic. No.: C39467 | 500 N BRAND BLVD #2000 GLENDALE, CA 91203 |
| Contractor | Owner-Builder | , |
| Engineer | Dahmen,, David Allen; Lic. No.: C17918 | 9739 N VISTA DR KINGMAN, AZ 864019426 |
| Engineer | Granata,, Salvatore; Lic. No.: C60382 | 11509 LODGEPOLE COURT SPANISH FORT, AL 36527 |
| Engineer | Hofmann,, Jeffrey Erwin; Lic. No.: C47407 | 9198 GREENBACK LN #116 ORANGEVALE, CA 95662 |
Inspector Information
| CASIMIR BRITTON, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
| SHAVONNE ESPINOZA, (310) 914-3913 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 1/30/2026 | Not Ready for Inspection | VASIL MIHALEV |
| Footing/Foundation/Slab | 1/30/2026 | Approved | VASIL MIHALEV |
| Green Building Final | 1/30/2026 | Not Ready for Inspection | VASIL MIHALEV |
| Green Building Rough | 1/30/2026 | Not Ready for Inspection | VASIL MIHALEV |
| SGSOV-Seismic Gas S/O Valve | 1/30/2026 | SGSOV Not Ready | VASIL MIHALEV |
| Smoke Detectors | 1/30/2026 | Approved | VASIL MIHALEV |
| Verify Sprinkler Sign Off | 1/30/2026 | Not Ready for Inspection | VASIL MIHALEV |
| Wood Frame | 1/30/2026 | Partial Approval | VASIL MIHALEV |
| Final | 6/8/2026 | Not Ready for Inspection | CASIMIR BRITTON |
| Green Building Final | 6/8/2026 | Approved | CASIMIR BRITTON |
| Green Building Rough | 6/8/2026 | Approved | CASIMIR BRITTON |
| SGSOV-Seismic Gas S/O Valve | 6/8/2026 | SGSOV Approved | CASIMIR BRITTON |
| Verify Sprinkler Sign Off | 6/8/2026 | Approved | CASIMIR BRITTON |
| Wood Frame | 6/8/2026 | Approved | CASIMIR BRITTON |
| Special/Order Compliance | 7/7/2026 | Partial Inspection | DANIEL VARNUM |