501 N MOUNT HOLYOKE AVE 90272
Certificate Information: 501 N MOUNT HOLYOKE AVE 90272
- Application / Permit
- 25010-30000-05587
- Plan Check / Job No.
- B25WL09112
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND ROOF DECK. (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 1/27/2026
- Issuing Office
- Current Status
- Issued on 1/27/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2025 | SELLA BENYAMIN |
| Corrections Issued | 12/2/2025 | SELLA BENYAMIN |
| Quality Review Completed | 12/4/2025 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 1/20/2026 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 1/27/2026 | MIROOSH KHACHATOORIAN |
| Issued | 1/27/2026 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2025 | MICHAEL BROWN |
| Permit | Cleared | 12/3/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 12/3/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 12/3/2025 | MICHAEL BROWN |
| Hydrant and Access approval | Cleared | 1/15/2026 | GILBERT URREA |
| Trees in Parkway | Cleared | 1/22/2026 | MIGUEL ORNELAS |
Contact Information
| Contractor | Meepos Home Builders Inc; Lic. No.: 1133726-B | 2999 OVERLAND AVE 130 LOS ANGELES, CA 90064 |
| Engineer | Kessler,, Dale Edward; Lic. No.: C58524 | 16043 HART ST VAN NUYS, CA 91406 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/15/2026 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 4/15/2026 | Partial Approval | STEPHANIE SWANSON |
| Deputy Steel/Welding | 5/4/2026 | Conditional Approval | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 5/5/2026 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 5/15/2026 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2026 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2026 | Partial Approval | STEPHANIE SWANSON |