951 N FISKE ST 90272
Certificate Information: 951 N FISKE ST 90272
- Application / Permit
- 25010-30000-05240
- Plan Check / Job No.
- B25WL08703
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY, 30' X 83'. NFPA 13D SPRINKLERS THROUGHOUT. EO1
- Permit Issued
- Issued on 12/23/2025
- Issuing Office
- Current Status
- Issued on 12/23/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2025 | SELLA BENYAMIN |
| Corrections Issued | 11/13/2025 | SELLA BENYAMIN |
| Quality Review Completed | 11/19/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 11/20/2025 | APPLICANT |
| Plan Check Approved | 12/16/2025 | SELLA BENYAMIN |
| Issued | 12/23/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/7/2025 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2025 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 11/7/2025 | STEVE MELGAR |
| Sewer availability | Cleared | 11/7/2025 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 11/20/2025 | PATRICK PEREZ |
Contact Information
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 200 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 15 STUDEBAKER IRVINE, CA 92618 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 2/26/2026 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 2/26/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Pre-Stress Concrete | 3/6/2026 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/9/2026 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 3/9/2026 | Approved | TEMISTOCLES CAAL |
| Deputy Pre-Stress Concrete | 3/25/2026 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2026 | Partial Approval | TEMISTOCLES CAAL |
| Deputy Wood Construction | 5/11/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2026 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2026 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2026 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2026 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2026 | Approved | JESUS PINEDA |
| PLUMBING-Final | 6/1/2026 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 6/4/2026 | Corrections Issued | EVAN COOPER |
| Gas Test | 6/4/2026 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 6/4/2026 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 6/11/2026 | Approved | JESUS PINEDA |
| HVAC-Rough | 6/11/2026 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 6/11/2026 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 6/12/2026 | Not Ready for Inspection | JESUS PINEDA |
| Green Building Rough | 6/12/2026 | Approved | JESUS PINEDA |
| Verify Sprinkler Sign Off | 6/12/2026 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/15/2026 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/16/2026 | Approved | TEMISTOCLES CAAL |
| Insulation | 6/22/2026 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/22/2026 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 7/1/2026 | Approved | ARAM AVEDISIAN |