11729 W TENNESSEE AVE 90064
Certificate Information: 11729 W TENNESSEE AVE 90064
- Application / Permit
- 25010-30000-05182
- Plan Check / Job No.
- B25WL08624
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new 2-story S.F.D. w/ attached garage NFPA 13D Fire Sprinkler all over.
- Permit Issued
- Issued on 4/16/2026
- Issuing Office
- Valley
- Current Status
- Issued on 4/16/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/31/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2025 | ZENA HADDIS |
| Assigned to Zoning Architect | 11/6/2025 | DAVID ZHENG |
| Corrections Issued | 11/26/2025 | ZENA HADDIS |
| Quality Review Completed | 12/2/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 12/3/2025 | APPLICANT |
| Plan Check Approved | 4/14/2026 | ZENA HADDIS |
| Issued | 4/16/2026 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/2/2025 | JESUS CISNEROS |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2025 | JESUS CISNEROS |
| Sewer availability | Cleared | 12/4/2025 | JESUS CISNEROS |
| Hydrant and Access approval | Cleared | 1/16/2026 | KURT CORRAL |
| Specific Plan | Cleared | 3/10/2026 | KYLE WINSTON |
| Specific Plan | Cleared | 3/10/2026 | KYLE WINSTON |
| CPC | Cleared | 3/16/2026 | MATHEW QUAN |
| Frnt yard landscape/Water mgmt | Cleared | 3/16/2026 | MATHEW QUAN |
| Specific Plan | Cleared | 3/18/2026 | RICHARD WOO |
| Zoning Plan Check | Cleared | 3/23/2026 | DAVID ZHENG |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Owner-Builder | , |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| PLUMBING-Rough | 7/22/2026 Time Frame: 10-12 |
| HVAC-Rough | 7/22/2026 Time Frame: 10-12 |
Inspection Request History
| Underground Mechanical | 4/24/2026 | Approved | WILBER ROSALES |
| Excavation/Setback/Form/Re-Bar | 5/1/2026 | Approved | RYAN SALAZAR |
| Footing/Foundation/Slab | 5/1/2026 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2026 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2026 | Partial Approval | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2026 | Approved | ANTHONY EGSON |