16988 W MARQUEZ AVE 90272

Certificate Information: 16988 W MARQUEZ AVE 90272

Application / Permit
25010-30000-05155
Plan Check / Job No.
B25WL08607
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, BASEMENT, (3)-STORY. NFPA 13D SPRINKLERS THROUGHOUTNFPA-13D FIRE SPRINKLERS THRU-OUT
Permit Issued
Issued on 1/8/2026
Issuing Office
Current Status
Issued on 1/8/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/30/2025 APPLICANT
Assigned to Plan Check Engineer 11/6/2025 MIROOSH KHACHATOORIAN
Corrections Issued 11/21/2025 MIROOSH KHACHATOORIAN
Quality Review Completed 11/23/2025 KAVIAN REFAHI
Applicant returned to address corrections 12/11/2025 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 12/22/2025 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 12/29/2025 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 1/6/2026 MIROOSH KHACHATOORIAN
Plan Check Approved 1/8/2026 MIROOSH KHACHATOORIAN
Issued 1/8/2026 APPLICANT

Permit Application Clearance Information

Address approval Cleared 11/25/2025 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 11/25/2025 DAVID LOPEZ
Roof/Waste drainage to street Cleared 11/25/2025 DAVID LOPEZ
Sewer availability Cleared 11/25/2025 DAVID LOPEZ
Low Impact Development (LID) Cleared 12/5/2025 MARCO SANCHEZ
Hydrant and Access approval Cleared 12/9/2025 JERRY KAO
GPI Written Notices Cleared 1/6/2026 MIROOSH KHACHATOORIAN

Contact Information

Contractor Vam Construction Corp; Lic. No.: 1078047-B 528 SALEM STREET      GLENDALE, CA 91203
Engineer Alrayes,, Nidham Aram; Lic. No.: C65487 3951 LOS OLIVOS LANE      LA CRESCENTA, CA 91214
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/13/2026 Partial Approval MEL KHACHATOURIAN
Masonry Wall/Backfill 3/2/2026 Partial Approval BOBBY KEY
Deputy Reinf. Masonry 3/6/2026 Conditional Approval JUAN VALENZUELA
PLUMBING-Rough 4/1/2026 Corrections Issued DANIEL VERA
Deputy Reinf. Masonry 4/22/2026 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 4/28/2026 Partial Approval DANIEL VERA
PLUMBING-Rough 4/28/2026 Partial Approval DANIEL VERA
Masonry Wall/Backfill 5/26/2026 Partial Approval MICHAEL ALLEN