919 N FISKE ST 90272

Certificate Information: 919 N FISKE ST 90272

Application / Permit
25010-30000-04985
Plan Check / Job No.
B25WL08388
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT. INELIGIBLE
Permit Issued
Issued on 12/24/2025
Issuing Office
Current Status
Issued on 12/24/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/23/2025 APPLICANT
Assigned to Plan Check Engineer 10/23/2025 SERGIO SILVA
Corrections Issued 11/17/2025 CHIHARU SUZUKI
Quality Review Completed 11/17/2025 CHIHARU SUZUKI
Building Plans Picked Up 11/24/2025 APPLICANT
Applicant returned to address corrections 12/8/2025 SERGIO SILVA
Plan Check Approved 12/15/2025 SERGIO SILVA
Issued 12/24/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 10/31/2025 DAVID VO
Eng Process Fee Ord 176,300 Cleared 10/31/2025 DAVID VO
Permit Cleared 10/31/2025 DAVID VO
Roof/Waste drainage to street Cleared 10/31/2025 DAVID VO
Sewer availability Cleared 10/31/2025 DAVID VO
Trees in Parkway Cleared 11/12/2025 MIGUEL ORNELAS
Low Impact Development (LID) Cleared 11/19/2025 ERNEST TSE
Hydrant and Access approval Cleared 11/20/2025 JERRY KAO
GPI Written Notices Cleared 12/15/2025 SERGIO SILVA
Grading Pre-Inspection Cleared 12/15/2025 SERGIO SILVA

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Sun Developers Inc; Lic. No.: 865631-B 23371 MULHOLLAND DRIVE 295      WOODLAND HILLS, CA 91364
Engineer Namdar,, Mansour; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/3/2026 Partial Approval MICHAEL ALLEN
Footing/Foundation/Slab 3/13/2026 Corrections Issued MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 3/23/2026 Approved MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 4/9/2026 Corrections Issued DANIEL VERA
PLUMBING-Rough 5/26/2026 Corrections Issued JESUS PINEDA
Sewer 5/26/2026 Corrections Issued JESUS PINEDA
HVAC-Rough 5/27/2026 Corrections Issued JESUS PINEDA
Sewer 5/27/2026 Approved JESUS PINEDA
Sewer 5/29/2026 No Access for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 6/8/2026 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/17/2026 Approved RYAN SALAZAR
Shower Pan 6/22/2026 Approved EVAN COOPER
PLUMBING-Rough 6/25/2026 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 6/29/2026 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 7/20/2026 Approved JESUS PINEDA
Green Building Rough 7/20/2026 Approved JESUS PINEDA
HVAC-Rough 7/20/2026 Approved JESUS PINEDA
Interior/Exterior Lathing 7/20/2026 Partial Approval JESUS PINEDA
PLUMBING-Rough 7/20/2026 Approved JESUS PINEDA
Verify Sprinkler Sign Off 7/20/2026 Approved JESUS PINEDA