950 N FISKE ST 90272
Certificate Information: 950 N FISKE ST 90272
- Application / Permit
- 25010-30000-04594
- Plan Check / Job No.
- B25WL07946
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT. EO1
- Permit Issued
- Issued on 11/24/2025
- Issuing Office
- Current Status
- Issued on 11/24/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/2/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2025 | SERGIO SILVA |
| Corrections Issued | 10/6/2025 | SERGIO SILVA |
| Quality Review Completed | 10/20/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 10/20/2025 | APPLICANT |
| Applicant returned to address corrections | 11/17/2025 | SERGIO SILVA |
| Plan Check Approved | 11/24/2025 | SERGIO SILVA |
| Issued | 11/24/2025 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/7/2025 | RUEL COLE |
| Address approval | Cleared | 10/8/2025 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2025 | BIAINA HARITUNIAN |
| Permit | Cleared | 10/8/2025 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 10/8/2025 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/8/2025 | BIAINA HARITUNIAN |
| Trees in Parkway | Cleared | 10/8/2025 | RICHARD SANCHEZ |
| Excavation more than 5-ft deep | Cleared | 11/24/2025 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 11/24/2025 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 11/24/2025 | SERGIO SILVA |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 200 ALISO VIEJO, CA 92656 |
| Engineer | Haddad,, Raymond M; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 15 STUDEBAKER IRVINE, CA 92618 |
| Engineer | Surur,, Shereef C; Lic. No.: L7295 | 2029 MILLCREEK WY PALMDALE, CA 93551 |
| Engineer | Toedter,, Randy; Lic. No.: S2991 | 689 COUNTY SQUARE DR UNIT 32 VENTURA, CA 93003 |
| Engineer | Waddell,, Ian R; Lic. No.: C41219 | 519 10TH ST HUNTINGTON BEACH, CA 92648 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Interior/Exterior Lathing | 6/22/2026 |
Inspection Request History
| Sewer | 2/12/2026 | Approved | MICHAEL ALLEN |
| Underground Mechanical | 2/12/2026 | Approved | MICHAEL ALLEN |
| Deputy Pre-Stress Concrete | 3/6/2026 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/9/2026 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 3/9/2026 | Approved | TEMISTOCLES CAAL |
| Deputy Pre-Stress Concrete | 3/25/2026 | Conditional Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2026 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2026 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2026 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2026 | Partial Inspection | JESUS PINEDA |
| PLUMBING-Rough | 5/29/2026 | Partial Approval | ARAM AVEDISIAN |
| Gas Test | 6/4/2026 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 6/4/2026 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 6/10/2026 | No Access for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 6/10/2026 | No Access for Inspection | TEMISTOCLES CAAL |
| Gas Test | 6/10/2026 | No Access for Inspection | TEMISTOCLES CAAL |
| Green Building Rough | 6/10/2026 | No Access for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 6/10/2026 | No Access for Inspection | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 6/10/2026 | No Access for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 6/12/2026 | Approved | JESUS PINEDA |
| HVAC-Rough | 6/12/2026 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 6/12/2026 | Approved | JESUS PINEDA |
| Wood Frame | 6/12/2026 | Not Ready for Inspection | JESUS PINEDA |
| Interior/Exterior Lathing | 6/15/2026 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 6/16/2026 | Conditional Approval | TEMISTOCLES CAAL |
| Green Building Rough | 6/16/2026 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 6/16/2026 | Approved | TEMISTOCLES CAAL |