14909 W SUNSET BLVD 90272
Certificate Information: 14909 W SUNSET BLVD 90272
- Application / Permit
- 25010-30000-04528
- Plan Check / Job No.
- B25WL07857
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND COVERED PATIO, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT INELIGIBLE
- Permit Issued
- Issued on 11/7/2025
- Issuing Office
- Current Status
- Issued on 11/7/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2025 | MADISON ODELL |
| Corrections Issued | 10/7/2025 | MADISON ODELL |
| Quality Review Completed | 10/14/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 10/15/2025 | APPLICANT |
| Plan Check Approved | 11/7/2025 | MADISON O'DELL |
| Issued | 11/7/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2025 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2025 | STEVE MELGAR |
| Permit | Cleared | 10/6/2025 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 10/6/2025 | STEVE MELGAR |
| Sewer availability | Cleared | 10/6/2025 | STEVE MELGAR |
| Hydrant and Access approval | Cleared | 10/7/2025 | JOHN CONNEALLY |
| Trees in Parkway | Cleared | 10/7/2025 | RICHARD SANCHEZ |
| Low Impact Development (LID) | Cleared | 10/8/2025 | MARTIN FRAGOSO |
| GPI Written Notices | Cleared | 11/7/2025 | MADISON O'DELL |
| Grading Pre-Inspection | Cleared | 11/7/2025 | MADISON O'DELL |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 200 ALISO VIEJO, CA 92656 |
| Engineer | Miller,, Karen Lynn; Lic. No.: GE2257 | 6634 VALJEAN AVENUE VAN NUYS, CA 91406 |
| Engineer | Nguyen,, Huan; Lic. No.: C64238 | 15 STUDEBAKER IRVINE, CA 92618 |
| Engineer | Toedter,, Randy; Lic. No.: S2991 | 689 COUNTY SQUARE DR UNIT 32 VENTURA, CA 93003 |
| Engineer | Waddell,, Ian R; Lic. No.: C41219 | 519 10TH ST HUNTINGTON BEACH, CA 92648 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
| Geologist | Ruberti,, Rudolph F; Lic. No.: EG1708 | 6634 VALJEAN AVE VAN NUYS, CA 91406 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/20/2026 | Corrections Issued | TEMISTOCLES CAAL |
| Sewer | 1/20/2026 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 1/21/2026 | Partial Approval | STEPHANIE SWANSON |
| Sewer | 1/21/2026 | Approved | STEPHANIE SWANSON |
| Deputy Pre-Stress Concrete | 1/29/2026 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 1/30/2026 | Approved | BOBBY KEY |
| Deputy Pre-Stress Concrete | 2/2/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 2/2/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2026 | Partial Approval | DANIEL VERA |
| Deputy Pre-Stress Concrete | 2/24/2026 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 3/12/2026 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2026 | Partial Approval | TEMISTOCLES CAAL |
| HVAC-Rough | 3/16/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 3/17/2026 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2026 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 4/7/2026 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 4/7/2026 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 4/13/2026 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 4/13/2026 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 4/13/2026 | Partial Approval | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 4/13/2026 | Approved | TEMISTOCLES CAAL |
| Insulation | 4/16/2026 | Approved | BOBBY KEY |
| Drywall Nailing | 4/27/2026 | Approved | JUAN VALENZUELA |
| Shower Pan | 5/26/2026 | Corrections Issued | JESUS PINEDA |
| Shower Pan | 5/28/2026 | Approved | ANDREW NAVE |