841 N CHAUTAUQUA BLVD 90272

Certificate Information: 841 N CHAUTAUQUA BLVD 90272

Application / Permit
25010-30000-04185
Plan Check / Job No.
B25WL07399
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/20/2026
Issuing Office
Current Status
Issued on 2/20/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/11/2025 APPLICANT
Assigned to Plan Check Engineer 9/15/2025 HERNAN ARREOLA
Corrections Issued 9/16/2025 HERNAN ARREOLA
Quality Review Completed 10/8/2025 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 12/4/2025 HERNAN ARREOLA
Plan Check Approved 2/19/2026 HERNAN ARREOLA
Issued 2/20/2026 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 11/6/2025 RUEL COLE
Hydrant and Access approval Cleared 11/6/2025 RUEL COLE
Eng Process Fee Ord 176,300 Cleared 12/9/2025 TONY CHIANG
Roof/Waste drainage to street Cleared 12/9/2025 TONY CHIANG
Sewer availability Cleared 12/9/2025 TONY CHIANG

Contact Information

Architect Bolander,, William Bruce; Lic. No.: C29808 2710 LAS FLORES CANYON ROAD      MALIBU, CA 90265
Contractor Lang Construction Company Inc; Lic. No.: 462162-B 31121 VIA COLINAS STE 1004      WESTLAKE VILLAGE, CA 91362
Engineer Perazzelli,, Joseph Ames; Lic. No.: C35270 183 GREENFIELD AVENUE      LOS ANGELES, CA 90049

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/25/2026 Not Ready for Inspection MEL KHACHATOURIAN
Pre-Inspection 2/25/2026 Approved MEL KHACHATOURIAN
Posting Pre-Inspection 2/26/2026 Approved MEL KHACHATOURIAN
Footing/Foundation/Slab 3/17/2026 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 4/29/2026 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 4/29/2026 Partial Approval TEMISTOCLES CAAL
Deputy Reinf. Concrete 5/4/2026 Conditional Approval JUAN VALENZUELA
Underground Mechanical 5/21/2026 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 5/28/2026 Approved JESUS PINEDA
Deputy Steel/Welding 7/22/2026 Conditional Approval TEMISTOCLES CAAL