6535 W COMMODORE SLOAT DR 90048
Certificate Information: 6535 W COMMODORE SLOAT DR 90048
- Application / Permit
- 25010-30000-04166
- Plan Check / Job No.
- B25WL07358
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- New detached garage with interior storage closet
- Permit Issued
- Issued on 3/26/2026
- Issuing Office
- Current Status
- Issued on 3/26/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/11/2025 | RICHARD GARCIA |
| Corrections Issued | 9/13/2025 | RICHARD GARCIA |
| Building Plans Picked Up | 9/17/2025 | APPLICANT |
| Plan Check Approved | 3/23/2026 | BEHROUZ KHOKHAR |
| Issued | 3/26/2026 | APPLICANT |
Permit Application Clearance Information
| HPOZ | Cleared | 11/21/2025 | LAMBERT GIESSINGER |
| Roof/Waste drainage to street | Cleared | 3/14/2026 | ARMEN MEHRABIAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2026 | ARMEN MEHRABIAN |
| CPC | Cleared | 3/23/2026 | DALIA MOKAYED |
Contact Information
| Contractor | Cox R H Inc; Lic. No.: 1038780-B | PO BOX 66188 LOS ANGELES, CA 90066 |
| Engineer | Brown,, Patrick John; Lic. No.: C45526 | 7 STARLING LAGUNA BEACH, CA 92656 |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Reinforced Masonry Frame | 6/11/2026 |
Inspection Request History
| Deputy Other (see comments) | 4/21/2026 | Conditional Approval | JOSH MEISTER |
| Excavation/Setback/Form/Re-Bar | 4/22/2026 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 4/22/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Barrier | 4/22/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Subgrade | 4/22/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Underground Mechanical | 4/22/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 4/30/2026 | Corrections Issued | RONNIE MINDANAO |
| Deputy Other (see comments) | 5/4/2026 | Conditional Approval | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 5/5/2026 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 5/5/2026 | Partial Approval | RONNIE MINDANAO |
| METHANE-Barrier | 5/5/2026 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Subgrade | 5/5/2026 | Approved | RONNIE MINDANAO |
| Deputy Methane Barrier | 5/18/2026 | Conditional Approval | RONNIE MINDANAO |
| METHANE-Barrier | 5/18/2026 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 5/18/2026 | Partial Approval | RONNIE MINDANAO |
| Footing/Foundation/Slab | 5/29/2026 | Approved | RONNIE MINDANAO |