822 N HARTZELL ST 90272
Certificate Information: 822 N HARTZELL ST 90272
- Application / Permit
- 25010-30000-04067
- Plan Check / Job No.
- B25WL07204
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, 2-STORY 32' X 80'-3". NFPA 13D SPRINKLERS THROUGHOUT. EO1 ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 10/17/2025
- Issuing Office
- Current Status
- Issued on 10/17/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/4/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/8/2025 | RAPHAEL ROSAS |
| Corrections Issued | 9/11/2025 | RAPHAEL ROSAS |
| Quality Review Completed | 9/11/2025 | STEVEN KIM |
| Building Plans Picked Up | 9/23/2025 | APPLICANT |
| Plan Check Approved | 10/9/2025 | RAPHAEL ROSAS |
| Issued | 10/17/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 9/11/2025 | CINDY QI |
| Sewer availability | Cleared | 9/11/2025 | CINDY QI |
| Hydrant and Access approval | Cleared | 9/15/2025 | JERRY KAO |
Contact Information
| Contractor | Dolan Design & Build Llc; Lic. No.: 1135363-B | 1817 IOWA TRAIL TOPANGA, CA 90290 |
| Engineer | Haddad,, Raymond M; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/6/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Rough | 11/10/2025 | Partial Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 11/13/2025 | Partial Approval | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 11/13/2025 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 11/13/2025 | Approved | TEMISTOCLES CAAL |
| Sewer | 11/25/2025 | Approved | MICHAEL ALLEN |
| Deputy Wood Construction | 12/1/2025 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2025 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2026 | Partial Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 1/27/2026 | Approved | TEMISTOCLES CAAL |
| Underground Mechanical | 1/27/2026 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 2/11/2026 | Approved | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/3/2026 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 3/3/2026 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 3/3/2026 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Rough | 3/3/2026 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 3/3/2026 | Partial Approval | TEMISTOCLES CAAL |
| Shower Pan | 3/3/2026 | Approved | TEMISTOCLES CAAL |
| Verify Sprinkler Sign Off | 3/3/2026 | Approved | TEMISTOCLES CAAL |
| Insulation | 3/31/2026 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 3/31/2026 | Partial Approval | MICHAEL ALLEN |
| Drywall Nailing | 4/14/2026 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 4/14/2026 | Approved | JUAN VALENZUELA |