10129 W LOVELANE PL 90064
Certificate Information: 10129 W LOVELANE PL 90064
- Application / Permit
- 25010-30000-04040
- Plan Check / Job No.
- B25WL07157
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 1-story detached ADU per LAMC 12.22 A.33(b)(1),(c),(d),(h) and (k)
- Permit Issued
- Issued on 11/10/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 11/10/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/3/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2025 | DAVID CASTILLO |
| Corrections Issued | 9/8/2025 | DAVID CASTILLO |
| Building Plans Picked Up | 9/8/2025 | APPLICANT |
| Applicant returned to address corrections | 11/7/2025 | BEHROUZ KHOKHAR |
| Plan Check Approved | 11/7/2025 | BEHROUZ KHOKHAR |
| No Progress | 11/7/2025 | BEHROUZ KHOKHAR |
| Plan Check Approved | 11/10/2025 | BEHROUZ KHOKHAR |
| Issued | 11/10/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/9/2025 | KATHLEEN LEE |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2025 | KATHLEEN LEE |
| Sewer availability | Cleared | 9/12/2025 | KATHLEEN LEE |
| Construction near power lines | Cleared | 10/7/2025 | ENRIQUE ACOSTA |
| Specific Plan | Cleared | 10/11/2025 | PEDRO AYALA |
| Address approval | Cleared | 11/7/2025 | KATHLEEN LEE |
| GPI Written Notices | Cleared | 11/7/2025 | DAVID CASTILLO |
| Grading Pre-Inspection | Cleared | 11/7/2025 | DAVID CASTILLO |
Contact Information
| Architect | Blumenberg,, Richard Leo; Lic. No.: C10862 | 11500 OLYMPIC BLVD #400 LOS ANGELES, CA 90064 |
| Contractor | Owner-Builder | , |
| Engineer | Bains,, Gagan Prit Singh; Lic. No.: S4482 | 222 E HUNTINGTON DR STE 235 MONROVIA, CA 91016 |
| Engineer | Yamashita,, Mark Alan; Lic. No.: L7155 | 6718 BIANCA AVE LAKE BALBOA, CA 91406 |
| Engineer | Zhong,, Raymond; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/26/2026 | Conditional Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/26/2026 | Approved | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 1/30/2026 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 2/2/2026 | Approved | ASHLEY THOMPSON |
| Deputy Reinf. Concrete | 2/4/2026 | Conditional Approval | DANIEL VERA |
| ELECTRICAL-Rough | 4/20/2026 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2026 | Conditional Approval | DANIEL VERA |
| Green Building Rough | 4/20/2026 | Not Ready for Inspection | DANIEL VERA |
| Verify Sprinkler Sign Off | 4/20/2026 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Rough | 4/21/2026 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 4/21/2026 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 5/4/2026 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 5/4/2026 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Rough | 5/4/2026 | Not Ready for Inspection | RYAN SALAZAR |
| PLUMBING-Rough | 5/4/2026 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 5/4/2026 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/13/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Rough | 5/13/2026 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 5/13/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| Insulation | 5/13/2026 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 5/13/2026 | Partial Approval | ASHLEY THOMPSON |
| Drywall Nailing | 6/2/2026 | Approved | ASHLEY THOMPSON |