1034 N LAS LOMAS AVE 90272
Certificate Information: 1034 N LAS LOMAS AVE 90272
- Application / Permit
- 25010-30000-03921
- Plan Check / Job No.
- B25WL06981
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 11/5/2025
- Issuing Office
- Current Status
- Issued on 11/5/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2025 | HERNAN ARREOLA |
| Corrections Issued | 9/3/2025 | HERNAN ARREOLA |
| Quality Review Completed | 9/3/2025 | CAROLYNN NEPOMUCENO |
| Building Plans Picked Up | 9/4/2025 | APPLICANT |
| Plan Check Approved | 10/30/2025 | HERNAN ARREOLA |
| Issued | 11/5/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/11/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 9/11/2025 | CINDY QI |
| Sewer availability | Cleared | 9/11/2025 | CINDY QI |
| Low Impact Development (LID) | Cleared | 9/12/2025 | LUIS LUVANO |
| Hydrant and Access approval | Cleared | 10/8/2025 | KURT CORRAL |
Contact Information
| Contractor | B W B Construction Inc; Lic. No.: 482140-B | 1119 LAS LOMAS AVE PACIFIC PALISADES, CA 90272 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Pre-Inspection | 7/13/2026 |
Inspection Request History
| Pre-Inspection | 11/25/2025 | Not Ready for Inspection | BOBBY KEY |
| Pre-Inspection | 5/29/2026 | Not Ready for Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 6/5/2026 | Corrections Issued | DANIEL VERA |
| Pre-Inspection | 6/5/2026 | Not Ready for Inspection | DANIEL VERA |
| Deputy Reinf. Concrete | 6/8/2026 | Conditional Approval | JUAN VALENZUELA |
| Pre-Inspection | 6/8/2026 | Not Ready for Inspection | DANIEL VERA |
| Piling/Pier/Caisson | 6/9/2026 | Partial Approval | DANIEL VERA |
| Deputy Reinf. Concrete | 6/11/2026 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 6/29/2026 | Corrections Issued | DANIEL VERA |
| Pre-Inspection | 6/29/2026 | Partial Inspection | DANIEL VERA |
| Footing/Foundation/Slab | 7/8/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Pre-Inspection | 7/8/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| Pre-Inspection | 7/10/2026 | No Result Entered | DANIEL VERA |