1157 N GALLOWAY ST 90272

Certificate Information: 1157 N GALLOWAY ST 90272

Application / Permit
25010-30000-03772
Plan Check / Job No.
B25WL06750
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE AND COVERED PATION, 2-STORY. NFPA 13D SPRINKLERS THROUGHOUT INELIGIBLE
Permit Issued
Issued on 10/30/2025
Issuing Office
Current Status
Issued on 10/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/19/2025 APPLICANT
Assigned to Plan Check Engineer 8/21/2025 JAD BASMA
Corrections Issued 8/24/2025 JAD BASMA
Quality Review Completed 8/25/2025 KEN GILL
Building Plans Picked Up 9/4/2025 APPLICANT
Plan Check Approved 10/17/2025 JAD BASMA
Issued 10/30/2025 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/25/2025 SAFA JAVANMARDI
Permit Cleared 8/25/2025 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 8/25/2025 SAFA JAVANMARDI
Sewer availability Cleared 8/25/2025 SAFA JAVANMARDI
Hydrant and Access approval Cleared 9/12/2025 PATRICK PEREZ
ZA Case Cleared 9/17/2025 DALIA MOKAYED
Trees in Parkway Cleared 9/30/2025 RICHARD SANCHEZ
GPI Written Notices Cleared 10/17/2025 JAD BASMA
Grading Pre-Inspection Cleared 10/17/2025 JAD BASMA

Contact Information

Architect , Scala; Lic. No.: C33220       ,
Contractor Sun Developers Inc; Lic. No.: 865631-B 23371 MULHOLLAND DRIVE 295      WOODLAND HILLS, CA 91364
Engineer Namdar, Engineering; Lic. No.: S2976       ,

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/22/2025 Partial Approval TEMISTOCLES CAAL
Excavation/Setback/Form/Re-Bar 1/14/2026 Approved DANIEL VERA
Floor/Roof Diaphrgm/Shear Wall 2/6/2026 Partial Approval TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 2/27/2026 Partial Approval TEMISTOCLES CAAL
HVAC-Rough 3/13/2026 Approved HERBERT GIRON
PLUMBING-Rough 3/19/2026 Approved EVAN COOPER
Interior/Exterior Lathing 3/31/2026 Partial Approval MICHAEL ALLEN
Shower Pan 3/31/2026 Partial Approval MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 4/17/2026 Partial Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 4/24/2026 Approved JESUS PINEDA
BUILDING-Rough-Frame 4/28/2026 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 4/28/2026 Approved TEMISTOCLES CAAL
Green Building Rough 4/28/2026 Approved TEMISTOCLES CAAL
Verify Sprinkler Sign Off 4/28/2026 Approved TEMISTOCLES CAAL
Insulation 5/4/2026 Approved JUAN VALENZUELA
Drywall Nailing 5/11/2026 Approved JESUS PINEDA