575 N TAHQUITZ PL 90272
Certificate Information: 575 N TAHQUITZ PL 90272
- Application / Permit
- 25010-30000-03766
- Plan Check / Job No.
- B25WL06731
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2025 WILDFIRE REBUILD, SINGLE-FAMILY DWELLING WITH AN ATTACHED GARAGE, (2)-STORY. NFPA 13D SPRINKLERS THROUGHOUT EO1
- Permit Issued
- Issued on 9/8/2025
- Issuing Office
- Current Status
- Issued on 9/8/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/19/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2025 | EDWIN ESPIN |
| Corrections Issued | 8/26/2025 | EDWIN ESPIN |
| Quality Review Completed | 8/27/2025 | CHIHARU SUZUKI |
| Building Plans Picked Up | 8/28/2025 | APPLICANT |
| Applicant returned to address corrections | 9/3/2025 | EDWIN ESPIN |
| Plan Check Approved | 9/5/2025 | EDWIN ESPIN |
| Issued | 9/8/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/25/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2025 | SAFA JAVANMARDI |
| Permit | Cleared | 8/25/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 8/25/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 8/25/2025 | SAFA JAVANMARDI |
| Coastal Zone | Cleared | 8/29/2025 | NOAH MCCOY |
| Hydrant and Access approval | Cleared | 8/29/2025 | JERRY KAO |
| Miscellaneous | Cleared | 8/29/2025 | NOAH MCCOY |
| Miscellaneous | Cleared | 8/29/2025 | NOAH MCCOY |
| Miscellaneous | Cleared | 8/29/2025 | NOAH MCCOY |
| ZA Case | Cleared | 8/29/2025 | NOAH MCCOY |
| ZI | Cleared | 8/29/2025 | NOAH MCCOY |
| GPI Written Notices | Cleared | 9/3/2025 | EDWIN ESPIN |
| Grading Pre-Inspection | Cleared | 9/3/2025 | EDWIN ESPIN |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Dolan Design & Build Llc; Lic. No.: 1135363-B | , |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
| Engineer | Toedter,, Randy; Lic. No.: S2991 | 689 COUNTY SQUARE DR UNIT 32 VENTURA, CA 93003 |
Inspector Information
| MEL KHACHATOURIAN, (213) 796-6439 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/27/2025 | Partial Approval | MEL KHACHATOURIAN |
| Excavation/Setback/Form/Re-Bar | 11/4/2025 | Approved | MEL KHACHATOURIAN |
| Deputy Wood Construction | 11/12/2025 | Conditional Approval | DAVID FEILER |
| Deputy Wood Construction | 11/13/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2025 | Partial Approval | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2025 | Partial Approval | MEL KHACHATOURIAN |
| Deputy Drilled-In Anchors | 12/23/2025 | Conditional Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 12/23/2025 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 12/29/2025 | Conditional Approval | MEL KHACHATOURIAN |
| HVAC-Rough | 1/7/2026 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 1/9/2026 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/27/2026 | Conditional Approval | MEL KHACHATOURIAN |
| Green Building Rough | 1/27/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 1/27/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 1/27/2026 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 2/13/2026 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 2/13/2026 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 2/13/2026 | Partial Approval | MEL KHACHATOURIAN |
| Insulation | 2/19/2026 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 2/27/2026 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 3/13/2026 | No Access for Inspection | MEL KHACHATOURIAN |
| Sewer | 3/17/2026 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 3/17/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Shower Pan | 3/18/2026 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 3/23/2026 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 4/1/2026 | Approved | EVAN COOPER |